Message ID: 239     Entry time: Wed Mar 6 15:33:14 2019
Author: Drive Team- Ino&Thierry&Armand 
Type: Telescope Operations 
Category: General 
Subject: Test High Speed Drive 
Status:  
  • Test at 60% maximal speed from -90 to 0
    •  Check of the FW discharge : No error (FW 2 : 95% FW1 : 100%)
  • Test at 60% maximal speed from -90 to 270
    • Check of the FW discharge ==> Error (FW 2 : 90 % FW1 : 100%)
    • Drive stops at 250 degree.
    • Power consumption = 60kw
  •  