== Monday July 5th ==
+
== Monday July 8th ==
  
 
* BP tests with Gustavo/Carlos?
 
* BP tests with Gustavo/Carlos?
Line 29: Line 29:
 
Sky data
 
Sky data
  
 +
== Tuesday July 9th ==
  
 +
Schneider people repair broken fans in IT container
  
 
== Wednesday July 10th ==
 
== Wednesday July 10th ==

Revision as of 16:38, 6 July 2019

P13 (8.7.2019 - 22.7.2019)

  • Commissioning Shift Period: 13
  • Dates: 8.7.2019 - 22.7.2019
  • Commissioning Shift Leader: Moritz Hütten
  • Commissioning Shifters / Experts:
    • Drive: (shift crew)
    • Camera: Taka, Yokiho Kobayashi, Mitsunari (from 27.6.)
    • AMC / Mirrors: (shift crew)
    • Former CSL: Dirk Hoffmann (until 7.7.)
    • Others:
  • Shifter: Noah Biederbeck (until 13.7.)


Planned actions

Monday July 8th

  • BP tests with Gustavo/Carlos?
    • test with TP and without HV where we perform the initialization, read the settings coarse and fine delay setting from the BP, using TP measure the up+down time, and repeat the cycle again, two or three times?


  • CaCo start-up checks, CaCo recovery, CaCo - EVB - TIB comm. (Mitsunari) ?

Night

Sky data

Tuesday July 9th

Schneider people repair broken fans in IT container

Wednesday July 10th

9-11: Casana finishes work in CC (floor of server compartment)

Tuesday July 16th

  • shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.)

Wednesday July 17th

  • shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.)