Difference between revisions of "Commissioning Shift P13"
(→Planned actions) |
(→Planned actions) |
||
Line 36: | Line 36: | ||
9-11: Casana finishes work in CC (floor of server compartment) | 9-11: Casana finishes work in CC (floor of server compartment) | ||
+ | |||
+ | == Thursday July 11th == | ||
+ | |||
+ | Javier Aragunde on site with José Ferraz company for LST-1 LPS | ||
== Tuesday July 16th == | == Tuesday July 16th == |
Revision as of 11:26, 7 July 2019
Contents
P13 (8.7.2019 - 22.7.2019)
- Commissioning Shift Period: 13
- Dates: 8.7.2019 - 22.7.2019
- Commissioning Shift Leader: Moritz Hütten
- Commissioning Shifters / Experts:
- Drive: (shift crew)
- Camera: Taka, Yokiho Kobayashi, Mitsunari (from 27.6.)
- AMC / Mirrors: (shift crew)
- Former CSL: Dirk Hoffmann (until 7.7.)
- Others:
- Shifter: Noah Biederbeck (until 13.7.)
Planned actions
Monday July 8th
- BP tests with Gustavo/Carlos?
- test with TP and without HV where we perform the initialization, read the settings coarse and fine delay setting from the BP, using TP measure the up+down time, and repeat the cycle again, two or three times?
- CaCo start-up checks, CaCo recovery, CaCo - EVB - TIB comm. (Mitsunari) ?
Night
Sky data
Tuesday July 9th
Schneider people repair broken fans in IT container
Wednesday July 10th
9-11: Casana finishes work in CC (floor of server compartment)
Thursday July 11th
Javier Aragunde on site with José Ferraz company for LST-1 LPS
Tuesday July 16th
- shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.)
Wednesday July 17th
- shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.)