Difference between revisions of "Commissioning Shift P13"
Line 57: | Line 57: | ||
* CaCo start-up checks, CaCo recovery, CaCo - EVB - TIB comm. (Mitsunari) | * CaCo start-up checks, CaCo recovery, CaCo - EVB - TIB comm. (Mitsunari) | ||
− | + | Night: Sky data | |
− | |||
− | Sky data | ||
== Tuesday July 9th == | == Tuesday July 9th == | ||
Line 72: | Line 70: | ||
9-11: Casana finishes work in CC (floor of server compartment) | 9-11: Casana finishes work in CC (floor of server compartment) | ||
− | + | Night: Drive tests? | |
− | Drive tests? | ||
== Thursday July 11th == | == Thursday July 11th == | ||
Javier Aragunde on site with José Ferraz company for LST-1 LPS | Javier Aragunde on site with José Ferraz company for LST-1 LPS | ||
+ | |||
+ | == Friday July 12th == | ||
+ | |||
+ | == Saturday July 13th == | ||
+ | |||
+ | no operations (weekend) | ||
+ | |||
+ | == Sunday July 14th == | ||
+ | |||
+ | no operations (weekend) | ||
+ | |||
+ | == Monday July 15th == | ||
+ | |||
+ | 11a.m.: Meeting with project manager in commissioning container | ||
== Tuesday July 16th == | == Tuesday July 16th == | ||
− | |||
* shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.) | * shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.) | ||
Line 87: | Line 97: | ||
* shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.) | * shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.) | ||
+ | |||
+ | == Thursday July 18th == | ||
+ | |||
+ | == Friday July 19th == | ||
+ | |||
+ | == Saturday July 20th == | ||
+ | |||
+ | no operations (weekend) | ||
+ | |||
+ | == Sunday July 21th == | ||
+ | |||
+ | no operations (weekend) |
Revision as of 11:18, 21 July 2019
Contents
- 1 P13 (8.7.2019 - 22.7.2019)
- 2 Regular datataking (continued as in P12)
- 3 Planned actions
- 3.1 Monday July 8th
- 3.2 Tuesday July 9th
- 3.3 Wednesday July 10th
- 3.4 Thursday July 11th
- 3.5 Friday July 12th
- 3.6 Saturday July 13th
- 3.7 Sunday July 14th
- 3.8 Monday July 15th
- 3.9 Tuesday July 16th
- 3.10 Wednesday July 17th
- 3.11 Thursday July 18th
- 3.12 Friday July 19th
- 3.13 Saturday July 20th
- 3.14 Sunday July 21th
P13 (8.7.2019 - 22.7.2019)
- Commissioning Shift Period: 13
- Dates: 8.7.2019 - 22.7.2019
- Commissioning Shift Leader: Moritz Hütten
- Commissioning Shifters / Experts:
- Drive: (shift crew)
- Camera: Taka, Yokiho Kobayashi, Mitsunari (from 27.6.)
- AMC / Mirrors: (shift crew)
- Former CSL: Dirk Hoffmann (until 7.7.)
- Others:
- Shifter: Noah Biederbeck (until 13.7.)
Regular datataking (continued as in P12)
Taken every night, if availability of staff (at least 1 shifter + 1 camera shifter + Commissioning Leader) and meteorological conditions (Watch humidity and temperature limits of camera!) allow.
Note all runs in eLog and RunCatalog!
- Prepare night data taking (last point), if applicable
- Unlock telescope
- Focus mirrors at sunset (not before!)
- HV off, shutter closed
- Pedestal 1kHz constant frequency (TIB-triggered): 100k events
- Pedestal 1kHz random (DRAGON-triggered): 100k events
- HV on (shutter still closed)
- Pedestal 1kHz constant frequency (TIB-triggered): 100k events
- Pedestal 1kHz random (DRAGON-triggered): 100k events
- Switch on calibration laser, if to be used later
- Park out telescope (earliest after sunset)
- HV on, shutter open
- Move to dark spot.
- Open the shutter in park position (ZA limit 60°!), but then move to dark spot (to avoid passing cars' lights).
- RA=211.08° / Dec=+29.52° is a good candidate for the dark spot; you may have others.
- MAGICs Dark Patch 05 at RA=256.25° / Dec=38.33°
- Pedestal 1kHz constant frequency (TIB-triggered): 100k events
- Pedestal 1kHz random (DRAGON-triggered): 100k events
- Calibration pulses (L1-triggered) 1kHz constant frequency
- Pointing and data taking
- Select a target (ask experts, or chose a reasonably active source)
- Kill noisy pixels
- Taka data for max. 1 hours
- Dont' forget the proper shutdown sequence of all elements!
Planned actions
Monday July 8th
- CaCo start-up checks, CaCo recovery, CaCo - EVB - TIB comm. (Mitsunari)
Night: Sky data
Tuesday July 9th
Schneider people repair broken fans in IT container (canceled because of incident)
BP tests with Gustavo/Carlos
- test with TP and without HV where we perform the initialization, read the settings coarse and fine delay setting from the BP, using TP measure the up+down time, and repeat the cycle again, two or three times?
Wednesday July 10th
9-11: Casana finishes work in CC (floor of server compartment)
Night: Drive tests?
Thursday July 11th
Javier Aragunde on site with José Ferraz company for LST-1 LPS
Friday July 12th
Saturday July 13th
no operations (weekend)
Sunday July 14th
no operations (weekend)
Monday July 15th
11a.m.: Meeting with project manager in commissioning container
Tuesday July 16th
- shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.)
Wednesday July 17th
- shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.)
Thursday July 18th
Friday July 19th
Saturday July 20th
no operations (weekend)
Sunday July 21th
no operations (weekend)