Difference between revisions of "Commissioning Shift P13"
(→Tuesday July 16th) |
(→Friday July 19th) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 113: | Line 113: | ||
== Wednesday July 17th == | == Wednesday July 17th == | ||
− | + | <del>shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.)</del> | |
+ | |||
+ | EVB and rate scan tests | ||
+ | |||
+ | Night: Pedestals; PSF camera and pointing tests by Tomo and Satoshi | ||
== Thursday July 18th == | == Thursday July 18th == | ||
+ | |||
+ | Evaluation of yesterday's tests/images | ||
+ | |||
+ | Introduction for subsequent CL | ||
+ | |||
+ | Night: Pedestals (again with HV?), star tracking for pointing offset tests | ||
== Friday July 19th == | == Friday July 19th == | ||
+ | |||
+ | Night: Pedestals (again with HV?), correct putative error from last night; continue tracking of Vega for pointing offset tests | ||
== Saturday July 20th == | == Saturday July 20th == |
Latest revision as of 11:51, 21 July 2019
Contents
- 1 P13 (8.7.2019 - 22.7.2019)
- 2 Regular datataking (continued as in P12)
- 3 Planned actions
- 3.1 Monday July 8th
- 3.2 Tuesday July 9th
- 3.3 Wednesday July 10th
- 3.4 Thursday July 11th
- 3.5 Friday July 12th
- 3.6 Saturday July 13th
- 3.7 Sunday July 14th
- 3.8 Monday July 15th
- 3.9 Tuesday July 16th
- 3.10 Wednesday July 17th
- 3.11 Thursday July 18th
- 3.12 Friday July 19th
- 3.13 Saturday July 20th
- 3.14 Sunday July 21th
P13 (8.7.2019 - 22.7.2019)[edit]
- Commissioning Shift Period: 13
- Dates: 8.7.2019 - 22.7.2019
- Commissioning Shift Leader: Moritz Hütten
- Commissioning Shifters / Experts:
- Drive: shift crew
- Camera: Taka (until 6.7.), Yokiho Kobayashi (until 13.7.), Mitsunari (from 27.6.)
- AMC / Mirrors: shift crew, Tomohiro (from 15.7.), Satoshi (from 17.7.)
- Former CSL: Dirk Hoffmann (until 7.7.)
- Others:
- Shifter: Noah Biederbeck (until 13.7.)
Regular datataking (continued as in P12)[edit]
Taken every night, if availability of staff (at least 1 shifter + 1 camera shifter + Commissioning Leader) and meteorological conditions (Watch humidity and temperature limits of camera!) allow.
Note all runs in eLog and RunCatalog!
- Prepare night data taking (last point), if applicable
- Unlock telescope
- Focus mirrors at sunset (not before!)
- HV off, shutter closed
- Pedestal 1kHz constant frequency (TIB-triggered): 100k events
- Pedestal 1kHz random (DRAGON-triggered): 100k events
- HV on (shutter still closed)
- Pedestal 1kHz constant frequency (TIB-triggered): 100k events
- Pedestal 1kHz random (DRAGON-triggered): 100k events
- Switch on calibration laser, if to be used later
- Park out telescope (earliest after sunset)
- HV on, shutter open
- Move to dark spot.
- Open the shutter in park position (ZA limit 60°!), but then move to dark spot (to avoid passing cars' lights).
- RA=211.08° / Dec=+29.52° is a good candidate for the dark spot; you may have others.
- MAGICs Dark Patch 05 at RA=256.25° / Dec=38.33°
- Pedestal 1kHz constant frequency (TIB-triggered): 100k events
- Pedestal 1kHz random (DRAGON-triggered): 100k events
- Calibration pulses (L1-triggered) 1kHz constant frequency
- Pointing and data taking
- Select a target (ask experts, or chose a reasonably active source)
- Kill noisy pixels
- Taka data for max. 1 hours
- Dont' forget the proper shutdown sequence of all elements!
Planned actions[edit]
Monday July 8th[edit]
CaCo start-up checks, CaCo recovery, CaCo - EVB - TIB comm. (Mitsunari)
Night: Sky data
Tuesday July 9th[edit]
Schneider people repair broken fans in IT container (canceled because of incident)
BP tests with Gustavo/Carlos
- test with TP and without HV where we perform the initialization, read the settings coarse and fine delay setting from the BP, using TP measure the up+down time, and repeat the cycle again, two or three times?
Night: drive tests with Ino (23:30 - 0:15)
Wednesday July 10th[edit]
9-11: Casana finishes work in CC (floor of server compartment)
Further investigate TIB failure problem (day and evening)
Night: Drive tests/reproduce TIB failure?
Thursday July 11th[edit]
Javier Aragunde on site with José Ferraz company for LST-1 LPS
Continue work on TIB failure
Search for dark patches with constraint of optimal moon distance
Night: Take data with HV and bright moonlight
Friday July 12th[edit]
Night: Dark spot observation (with HV?) at moonlight
Saturday July 13th[edit]
no operations (weekend)
Sunday July 14th[edit]
no operations (weekend)
Monday July 15th[edit]
11a.m.: Meeting with project manager in commissioning container
Control EVBv3 over CaCo
Night: take pedestals with shutter open (HV at bright moonlight?). Star tracking for PSF studies
Tuesday July 16th[edit]
shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.)
Night: Check with Carlos Diaz setting of SIS plate with OPCUA. Taking pedestal data
Wednesday July 17th[edit]
shutdown of energy storage container during whole day (No electricity in the telescope, Commissioning container and IT container will not be affected.)
EVB and rate scan tests
Night: Pedestals; PSF camera and pointing tests by Tomo and Satoshi
Thursday July 18th[edit]
Evaluation of yesterday's tests/images
Introduction for subsequent CL
Night: Pedestals (again with HV?), star tracking for pointing offset tests
Friday July 19th[edit]
Night: Pedestals (again with HV?), correct putative error from last night; continue tracking of Vega for pointing offset tests
Saturday July 20th[edit]
no operations (weekend)
Sunday July 21th[edit]
no operations (weekend)