Difference between revisions of "Logbook RailAndCentralPin"

From my_wiki
Jump to: navigation, search
(Enter comments in reverse time order)
(Entries made for first installation period.)
Line 6: Line 6:
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-03 || Wetteskind, Stadler, Wunderl || Arrival in La Palma || Safetly arrived in La Palma. Checked in in the hotel.||
+
| 2017-08-07 || Wetteskind, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-08-05 || Wetteskind, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-08-04 || Wetteskind, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-08-03 || Wetteskind, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-08-02 || Wetteskind, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-08-01 || Wetteskind, Stadler, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-31 || Wetteskind, Stadler, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-29 || Wetteskind, Stadler, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-28 || Wetteskind, Stadler, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-27 || Wetteskind, Stadler, Stürzer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-27 || Wetteskind, Stadler || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-27 || Jablonski, Stürzer || Installation of Central Pin || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-26 || Wetteskind || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-26 || Jablonski || Installation of Central Pin || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-25 || Wetteskind, Schlammer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-25 || Jablonski, Dettlaff || Installation of Central Pin || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-25 || Wetteskind, Schlammer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-25 || Jablonski, Dettlaff || Installation of Central Pin || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-24 || Wetteskind, Schlammer || Installation of Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-24 || Jablonski, Dettlaff || Installation of Central Pin || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-21 || Wetteskind, Schlammer || Installation of Rail || Further setting up of the rail onto the pedestals and removal of airpads. Checking of rail height and distance to the foundation center. ||
 +
 
 +
|- valign="top"
 +
| 2017-07-21 || Jablonski, Dettlaff || Installation of Central Pin || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-20 || Wetteskind, Schlammer || Installation of Rail || Starting of setting up the rail onto the pedestals and removal of airpads. Checking of rail height and distance to the foundation center. ||
 +
 
 +
|- valign="top"
 +
| 2017-07-20 || Jablonski, Dettlaff || Installation of Central Pin || Placing of central pin at foundation center... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-19 || Jablonski, Schlammer, Dettlaff || Installation of Central Pin and Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-18 || Jablonski, Wunderl, Schlammer, Dettlaff || Installation of Central Pin and Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-12 || Jablonski, Stadler, Wunderl, Schlammer || Installation of Central Pin and Rail || ... ||
 +
 
 +
|- valign="top"
 +
| 2017-07-11 || Jablonski, Stadler, Wunderl, Schlammer || Installation of Rail || Tightening of screws around the running surface of the rail. Assembly of connection plates between segment faces. Discovering a misalignment of some connection plates with holes on the segment faces. Checking of rail height and distance to the foundation center. ||
 +
 
 +
|- valign="top"
 +
| 2017-07-10 || Wetteskind, Stadler, Wunderl, Schlammer || Installation of Rail || Preparation of pneumatic connections between compressors and airpads. Positioning of grippers for pulling rail segments horizontally against foundation center. Closing gap by controlled pulling of segments at different positions while airpads are stowed by compressed air. Starting assembly of rail pedestals. ||
 +
 
 +
|- valign="top"
 +
| 2017-07-08 || Wetteskind, Stadler, Wunderl, Schlammer || Installation of Rail || Placing of remaining 3 rail segments on top of airpads. Again align them in height and distance to the foundation center. Placing of last segment with a gap of ~30 mm to the next-to-last segment. ||
 +
 
 +
|- valign="top"
 +
| 2017-07-07 || Wetteskind, Stadler, Wunderl, Schlammer || Installation of Rail || Placing of next 7 rail segments on top of airpads. Again align them in height and distance to the foundation center. ||
 +
 
 +
|- valign="top"
 +
| 2017-07-06 || Wetteskind, Stadler, Wunderl, Schlammer || Installation of Rail || Placing second rail segment on top of next two airpads. Installation order of segments has to be counter-clockwise when looking from top onto the foundation. Align both segments in height and distance (radius) to the foundation center. ||
 +
 
 +
|- valign="top"
 +
| 2017-07-05 || Wetteskind, Stadler, Wunderl, Schlammer || Installation of Rail || Placing first two airpads and align them in height. Placing first rail segment on top of the airpads. Placing and alignment of next airpads. ||
 +
 
 +
|- valign="top"
 +
| 2017-07-04 || Wetteskind, Stadler, Wunderl, Schlammer || Preparation of Site || Preparation of all needed tools and measurement devices. Checking of proper vertical distance between concrete ring and rail. Making marks on foundation for placing airpads. ||

Revision as of 22:49, 4 August 2017

Enter comments in reverse time order

Date Who did it? Action Comments Documents
2017-08-07 Wetteskind, Stürzer Installation of Rail ...
2017-08-05 Wetteskind, Stürzer Installation of Rail ...
2017-08-04 Wetteskind, Stürzer Installation of Rail ...
2017-08-03 Wetteskind, Stürzer Installation of Rail ...
2017-08-02 Wetteskind, Stürzer Installation of Rail ...
2017-08-01 Wetteskind, Stadler, Stürzer Installation of Rail ...
2017-07-31 Wetteskind, Stadler, Stürzer Installation of Rail ...
2017-07-29 Wetteskind, Stadler, Stürzer Installation of Rail ...
2017-07-28 Wetteskind, Stadler, Stürzer Installation of Rail ...
2017-07-27 Wetteskind, Stadler, Stürzer Installation of Rail ...
2017-07-27 Wetteskind, Stadler Installation of Rail ...
2017-07-27 Jablonski, Stürzer Installation of Central Pin ...
2017-07-26 Wetteskind Installation of Rail ...
2017-07-26 Jablonski Installation of Central Pin ...
2017-07-25 Wetteskind, Schlammer Installation of Rail ...
2017-07-25 Jablonski, Dettlaff Installation of Central Pin ...
2017-07-25 Wetteskind, Schlammer Installation of Rail ...
2017-07-25 Jablonski, Dettlaff Installation of Central Pin ...
2017-07-24 Wetteskind, Schlammer Installation of Rail ...
2017-07-24 Jablonski, Dettlaff Installation of Central Pin ...
2017-07-21 Wetteskind, Schlammer Installation of Rail Further setting up of the rail onto the pedestals and removal of airpads. Checking of rail height and distance to the foundation center.
2017-07-21 Jablonski, Dettlaff Installation of Central Pin ...
2017-07-20 Wetteskind, Schlammer Installation of Rail Starting of setting up the rail onto the pedestals and removal of airpads. Checking of rail height and distance to the foundation center.
2017-07-20 Jablonski, Dettlaff Installation of Central Pin Placing of central pin at foundation center...
2017-07-19 Jablonski, Schlammer, Dettlaff Installation of Central Pin and Rail ...
2017-07-18 Jablonski, Wunderl, Schlammer, Dettlaff Installation of Central Pin and Rail ...
2017-07-12 Jablonski, Stadler, Wunderl, Schlammer Installation of Central Pin and Rail ...
2017-07-11 Jablonski, Stadler, Wunderl, Schlammer Installation of Rail Tightening of screws around the running surface of the rail. Assembly of connection plates between segment faces. Discovering a misalignment of some connection plates with holes on the segment faces. Checking of rail height and distance to the foundation center.
2017-07-10 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Preparation of pneumatic connections between compressors and airpads. Positioning of grippers for pulling rail segments horizontally against foundation center. Closing gap by controlled pulling of segments at different positions while airpads are stowed by compressed air. Starting assembly of rail pedestals.
2017-07-08 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Placing of remaining 3 rail segments on top of airpads. Again align them in height and distance to the foundation center. Placing of last segment with a gap of ~30 mm to the next-to-last segment.
2017-07-07 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Placing of next 7 rail segments on top of airpads. Again align them in height and distance to the foundation center.
2017-07-06 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Placing second rail segment on top of next two airpads. Installation order of segments has to be counter-clockwise when looking from top onto the foundation. Align both segments in height and distance (radius) to the foundation center.
2017-07-05 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Placing first two airpads and align them in height. Placing first rail segment on top of the airpads. Placing and alignment of next airpads.
2017-07-04 Wetteskind, Stadler, Wunderl, Schlammer Preparation of Site Preparation of all needed tools and measurement devices. Checking of proper vertical distance between concrete ring and rail. Making marks on foundation for placing airpads.