| 2017-08-23 || Wetteskind, Schröder || Installation of Rail || ||
+
| 2017-08-29 || Wetteskind, Schröder || Installation of Rail || We finalize the mounting of cover plates on top of the rack. Last measurement of the inner and outer radius of rail runway in height and distance to foundation center. We did this measurement early in the morning before sunrise. After that we removed the measurement jig on top of the central pin. ||
  
 
|- valign="top"
 
|- valign="top"
| 2017-08-22 || Wetteskind, Schröder || Installation of Rail || Dragados proceeds to drill out the iron from the holes for anchors with a special drilling tool. Measuring inner radius of rail runway in height and distance to foundation center. Measuring central pin in height and centering (control measurement after last concrete pouring). Tighten srews of remaining rack segments installed with a torque of 2000 Nm (M30-10.9). ||
+
| 2017-08-28 || Wetteskind, Schröder || Installation of Rail || We start the mounting of cover plates on top of the rack. This day the reshuffling of MERO containers took place (together with the removal of rail containers). ||
 +
 
 +
|- valign="top"
 +
| 2017-08-26 || Wetteskind, Schröder || Installation of Rail || Measurement of the outer radius of rail runway in height and distance to foundation center. This measurement took all day long as we had to make three station movings. ||
 +
 
 +
|- valign="top"
 +
| 2017-08-25 || Wetteskind, Schröder || Installation of Rail || We finalize the tightening of the screws at the faces of the rail with a torque of 800 Nm (M30). ||
 +
 
 +
|- valign="top"
 +
| 2017-08-24 || Wetteskind, Schröder || Installation of Rail || We start to tighten the screws at the faces of the rail with a torque of 800 Nm (M30). ||
 +
 
 +
|- valign="top"
 +
| 2017-08-23 || Wetteskind, Schröder || Installation of Rail || Removing screws on the lower cord of three rail faces because they stick into the grout. Shorten these screws and mount them again. Drill out of the iron from the holes for anchors finalized by Dragados. ||
 +
 
 +
|- valign="top"
 +
| 2017-08-22 || Wetteskind, Schröder || Installation of Rail || Dragados proceeds to drill out the iron from the holes for anchors with a special drilling tool. Measuring inner radius of rail runway in height and distance to foundation center during lunch time. Measuring central pin in height and centering (control measurement after last concrete pouring). Tighten srews of remaining rack segments installed with a torque of 2000 Nm (M30-10.9). ||
  
 
|- valign="top"
 
|- valign="top"
Line 54: Line 69:
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-27 || Jablonski, Stürzer || Installation of Central Pin || ... ||
+
| 2017-07-27 || Jablonski, Stürzer || Installation of Central Pin || Checking position of central pin. No movement. Removal of Elevationdrivepodest from container. ||
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-26 || Wetteskind || Installation of Rail || Readjustment of pedestals with the goal to level them out. Attempt to reduce effect of friction.||
+
| 2017-07-26 || Wetteskind || Installation of Rail || Readjustment of pedestals with the goal to level them out. Attempt to reduce effect of friction. Removal of fluid rubber on top part of anchor bars.||
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-26 || Jablonski || Installation of Central Pin || ... ||
+
| 2017-07-26 || Jablonski || Installation of Central Pin || Checking position of central pin. No movement. Positioning rods tightened. ||
  
 
|- valign="top"
 
|- valign="top"
Line 66: Line 81:
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-25 || Jablonski, Dettlaff || Installation of Central Pin || ... ||
+
| 2017-07-25 || Jablonski, Dettlaff || Installation of Central Pin || Repeating measurment of central pin. Movement of 1mm realignment. ||
  
 
|- valign="top"
 
|- valign="top"
Line 72: Line 87:
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-24 || Jablonski, Dettlaff || Installation of Central Pin || ... ||
+
| 2017-07-24 || Jablonski, Dettlaff || Installation of Central Pin || Leveling of Bearinghead with Top Cross. Installation of 16x rubber sealing for anchor-rods of central pin. Tightening of flange on bottom of central pin. Alignment of central pin with TDRA 6000 relativ to telescope coord system. Filling of top part of anchor rods with fluid rubber (Kemperol).  ||
  
 
|- valign="top"
 
|- valign="top"
Line 78: Line 93:
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-21 || Jablonski, Dettlaff || Installation of Central Pin || ... ||
+
| 2017-07-21 || Jablonski, Dettlaff || Installation of Central Pin || Alignment of pin. Preparation to fill top part of anchor bars with fluid rubber. ||
  
 
|- valign="top"
 
|- valign="top"
Line 84: Line 99:
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-20 || Jablonski, Dettlaff || Installation of Central Pin || Placing of central pin at foundation center... ||
+
| 2017-07-20 || Jablonski, Dettlaff || Installation of Central Pin || Installing Adjustable feet for Central Pin. Placing of central pin at foundation center. First measure of central pin ||
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-19 || Jablonski, Schlammer, Dettlaff || Installation of Central Pin and Rail || ... ||
+
| 2017-07-19 || Jablonski, Schlammer, Dettlaff || Installation of Central Pin and Rail || Measuring and aligning rail. Measure points at connection. control of height and radius.||
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-18 || Jablonski, Wunderl, Schlammer, Dettlaff || Installation of Central Pin and Rail || ... ||
+
| 2017-07-18 || Jablonski, Wunderl, Schlammer, Dettlaff || Installation of Central Pin and Rail || Loosening of cooper plates. Checking and loosening of pedestals. ||
  
 
|- valign="top"
 
|- valign="top"
| 2017-07-12 || Jablonski, Stadler, Wunderl, Schlammer || Installation of Central Pin and Rail || ... ||
+
| 2017-07-12 || Jablonski, Stadler, Wunderl, Schlammer || Installation of Central Pin and Rail || Checking Central pin and additional parts. ||
  
 
|- valign="top"
 
|- valign="top"

Latest revision as of 13:45, 1 September 2017

Enter comments in reverse time order[edit]

Date Who did it? Action Comments Documents
2017-08-29 Wetteskind, Schröder Installation of Rail We finalize the mounting of cover plates on top of the rack. Last measurement of the inner and outer radius of rail runway in height and distance to foundation center. We did this measurement early in the morning before sunrise. After that we removed the measurement jig on top of the central pin.
2017-08-28 Wetteskind, Schröder Installation of Rail We start the mounting of cover plates on top of the rack. This day the reshuffling of MERO containers took place (together with the removal of rail containers).
2017-08-26 Wetteskind, Schröder Installation of Rail Measurement of the outer radius of rail runway in height and distance to foundation center. This measurement took all day long as we had to make three station movings.
2017-08-25 Wetteskind, Schröder Installation of Rail We finalize the tightening of the screws at the faces of the rail with a torque of 800 Nm (M30).
2017-08-24 Wetteskind, Schröder Installation of Rail We start to tighten the screws at the faces of the rail with a torque of 800 Nm (M30).
2017-08-23 Wetteskind, Schröder Installation of Rail Removing screws on the lower cord of three rail faces because they stick into the grout. Shorten these screws and mount them again. Drill out of the iron from the holes for anchors finalized by Dragados.
2017-08-22 Wetteskind, Schröder Installation of Rail Dragados proceeds to drill out the iron from the holes for anchors with a special drilling tool. Measuring inner radius of rail runway in height and distance to foundation center during lunch time. Measuring central pin in height and centering (control measurement after last concrete pouring). Tighten srews of remaining rack segments installed with a torque of 2000 Nm (M30-10.9).
2017-08-21 Wetteskind Installation of Rail 39 holes for anchors are not deep enough because of hitting iron during drilling. Dragados starts to drill out the iron with a special drilling tool. Preparation of site for assembly and integration of bogies (by IFAE people, see separate log book?). Preparation of wooden pieces to support azimuth bogie knots after integration onto the bogies (to prevent tilting of knots).
2017-08-16 to 2017-08-17 DRAGADOS Installation of Rail Proceeding with drilling of holes through pedestals into the foundation for anchors and gluing them into holes.
2017-08-11 DRAGADOS Installation of Rail Removal of mold for last concrete pouring at central pin. Proceeding with drilling of holes through pedestals into the foundation for anchors and gluing them into holes.
2017-08-10 DRAGADOS Installation of Rail Pouring the last quarter of rail ring with grout inbetween pedestals. Drilling of further holes through pedestals into the foundation for anchors. Gluing of anchors into holes.
2017-08-09 DRAGADOS Installation of Rail Pouring of concrete at central pin. Preparation of formwork for the last quarter of rail ring.
2017-08-08 Wetteskind, Stürzer Installation of Rail Installation of remaining rack segments (with crane). Fixation of screws only with low torque. Clean-up of site. Boxes with elevation drive arch shifted closer to the fence. Emptying of MBM containers (bogies with accessories shifted to the foundation of the camera access tower). Measuring inner radius of rail runway in height and distance to foundation center. Measuring central pin in height and centering (control measurement before last concrete pouring). Pouring the third quarter of rail ring with grout inbetween pedestals (done by Dragados). Preparation of mold for last concrete pouring at central pin (done by Dragados). Pouring is foreseen with fibrated concrete (quality H-35) to reduce cracks after hardening.
2017-08-07 Wetteskind, Stürzer Installation of Rail Tighten srews of first 4 rack segments installed with a torque of 2000 Nm (M30-10.9). Glueing test with 5 anchors for pedestals (glue amount per hole is 110 ml). Problems with screws fixing the lower connections plates: They are a bit too long (stick out of the plates and into the grout). They have to be exchanged against shorter ones. Preparation of formwork for the third quarter of rail ring (done by Dragados).
2017-08-05 Wetteskind, Stürzer Installation of Rail Measuring inner radius of rail runway in height and distance to foundation center. Clean-up of site.
2017-08-04 Wetteskind, Stürzer Installation of Rail Measuring outer radius of rail runway in height and distance to foundation center. Pouring the second quarter of rail ring with grout inbetween pedestals (done by Dragados). Performing further test drills through pedestals into foundation for anchors (done by Dragados).
2017-08-03 Wetteskind, Stürzer Installation of Rail Finalization of height adjustment of pedestals. Preparation of formwork for the second quarter of rail ring (done by Dragados). Performing first test drills through pedestals into foundation for anchors (done by Dragados).
2017-08-02 Wetteskind, Stürzer Installation of Rail Further adjustment of pedestals in height. Pouring the first quarter of rail ring with grout inbetween pedestals (done by Dragados).
2017-08-01 Wetteskind, Stadler, Stürzer Installation of Rail Starting with final adjustment of pedestals in height (inside and outside of rail ring). Preparation of formwork for the first quarter of rail ring (done by Dragados).
2017-07-28 - 2017-07-31 Wetteskind, Stadler, Stürzer Installation of Rail Installation of 4 rack segments on top of the rail (with forklifter). Further investigation of rail behaviour. Trying to improve the situation with different measures (e.g opening and closing connection plates between segment faces) - without success. Decision: We ignore this problem for the time being and concentrate on the final adjustment of pedestals (levelling them all in the same height).
2017-07-27 Wetteskind, Stadler Installation of Rail Remeasuring rail height and distance to foundation center. No improvement of rail tilting observed. Restarting of pedestal adjustment. We think a deeper investigation of the rail behaviour is useful.
2017-07-27 Jablonski, Stürzer Installation of Central Pin Checking position of central pin. No movement. Removal of Elevationdrivepodest from container.
2017-07-26 Wetteskind Installation of Rail Readjustment of pedestals with the goal to level them out. Attempt to reduce effect of friction. Removal of fluid rubber on top part of anchor bars.
2017-07-26 Jablonski Installation of Central Pin Checking position of central pin. No movement. Positioning rods tightened.
2017-07-25 Wetteskind, Schlammer Installation of Rail Early measurement of rail height and distance to the foundation center during dawn. Found same tilting around rail cross section axis but effect is less and in reverse order than measured the day before (height of rail running surface at outer radius partly bigger than at the inner one).
2017-07-25 Jablonski, Dettlaff Installation of Central Pin Repeating measurment of central pin. Movement of 1mm realignment.
2017-07-24 Wetteskind, Schlammer Installation of Rail Final setting down of the rail onto the pedestals and removal of airpads. Checking of rail height and distance to the foundation center. Detecting tilting of rail around its cross section axis. Effect was found about noon and results in bigger height of rail running surface at the inner radius than at the outer one. Assuming effect is due to thermal expansion in combination with friction between rail base and sliding plates of pedestals.
2017-07-24 Jablonski, Dettlaff Installation of Central Pin Leveling of Bearinghead with Top Cross. Installation of 16x rubber sealing for anchor-rods of central pin. Tightening of flange on bottom of central pin. Alignment of central pin with TDRA 6000 relativ to telescope coord system. Filling of top part of anchor rods with fluid rubber (Kemperol).
2017-07-21 Wetteskind, Schlammer Installation of Rail Further setting down of the rail onto the pedestals and removal of airpads. Checking of rail height and distance to the foundation center.
2017-07-21 Jablonski, Dettlaff Installation of Central Pin Alignment of pin. Preparation to fill top part of anchor bars with fluid rubber.
2017-07-20 Wetteskind, Schlammer Installation of Rail Starting of setting down the rail onto the pedestals and removal of airpads. Checking of rail height and distance to the foundation center.
2017-07-20 Jablonski, Dettlaff Installation of Central Pin Installing Adjustable feet for Central Pin. Placing of central pin at foundation center. First measure of central pin
2017-07-19 Jablonski, Schlammer, Dettlaff Installation of Central Pin and Rail Measuring and aligning rail. Measure points at connection. control of height and radius.
2017-07-18 Jablonski, Wunderl, Schlammer, Dettlaff Installation of Central Pin and Rail Loosening of cooper plates. Checking and loosening of pedestals.
2017-07-12 Jablonski, Stadler, Wunderl, Schlammer Installation of Central Pin and Rail Checking Central pin and additional parts.
2017-07-11 Jablonski, Stadler, Wunderl, Schlammer Installation of Rail Tightening of screws around the running surface of the rail. Assembly of connection plates between segment faces. Discovering a misalignment of some connection plates with holes on the segment faces. Checking of rail height and distance to the foundation center.
2017-07-10 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Preparation of pneumatic connections between compressors and airpads. Positioning of grippers for pulling rail segments horizontally against foundation center. Closing gap by controlled pulling of segments at different positions while airpads are stowed by compressed air. Starting assembly of rail pedestals.
2017-07-08 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Placing of remaining 3 rail segments on top of airpads. Again align them in height and distance to the foundation center. Placing of last segment with a gap of ~30 mm to the next-to-last segment.
2017-07-07 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Placing of next 7 rail segments on top of airpads. Again align them in height and distance to the foundation center.
2017-07-06 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Placing second rail segment on top of next two airpads. Installation order of segments has to be counter-clockwise when looking from top onto the foundation. Align both segments in height and distance (radius) to the foundation center.
2017-07-05 Wetteskind, Stadler, Wunderl, Schlammer Installation of Rail Placing first two airpads and align them in height. Placing first rail segment on top of the airpads. Placing and alignment of next airpads.
2017-07-04 Wetteskind, Stadler, Wunderl, Schlammer Preparation of Site Preparation of all needed tools and measurement devices. Checking of proper vertical distance between concrete ring and rail. Making marks on foundation for placing airpads.