Difference between revisions of "Logbook Permissions"
(→Enter comments in reverse time order) |
(→Enter comments in reverse time order) |
||
Line 5: | Line 5: | ||
! style="width: 100px;" | Date !! style="width: 200px;" | Who did it? !! style="width: 200px;" | Action !! style="width: 500px;" | Comments !! style="width: 200px;" | Documents | ! style="width: 100px;" | Date !! style="width: 200px;" | Who did it? !! style="width: 200px;" | Action !! style="width: 500px;" | Comments !! style="width: 200px;" | Documents | ||
|- valign="top" | |- valign="top" | ||
− | | 2014-10-01 || Cortina || Started bidding to hire foundation architect || | + | | 2014-10-01 || Cortina || Started bidding to hire foundation architect || || |
|- valign="top" | |- valign="top" | ||
− | | 2014-12-15 || Cortina || Contract between IFAE and architect signed || | + | | 2014-12-15 || Cortina || Contract between IFAE and architect signed || || |
|- valign="top" | |- valign="top" | ||
− | | 2015-03-15 || Architect || Foundation preliminary drawings ("pre-project") finished ||| | + | | 2015-03-15 || Architect || Foundation preliminary drawings ("pre-project") finished || || |
|- valign="top" | |- valign="top" | ||
| 2015-03-16 || IFAE/Architect || Request first step of license for foundation ("recalificación") ||| | | 2015-03-16 || IFAE/Architect || Request first step of license for foundation ("recalificación") ||| |
Revision as of 14:54, 5 September 2017
Enter comments in reverse time order
Date | Who did it? | Action | Comments | Documents | |||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2014-10-01 | Cortina | Started bidding to hire foundation architect | |||||||||||||||||||||||||||||||||||||
2014-12-15 | Cortina | Contract between IFAE and architect signed | |||||||||||||||||||||||||||||||||||||
2015-03-15 | Architect | Foundation preliminary drawings ("pre-project") finished | |||||||||||||||||||||||||||||||||||||
2015-03-16 | IFAE/Architect | Request first step of license for foundation ("recalificación") | 2015-10-22 | Cabildo | Cabildo issues first step of license for foundation | 2015-11-09 | Architect's association | La Palma architect's official association accepts final foundation drawings ("project") | 2015-12-11 | IAC | Tender for foundation published (in Spanish BOE) | 2016-05-10 | IAC | Tender finishes. Company Dragados selected | 2016-05-11 | Garafia | Town hall of Garafia issues second step of license for foundation | 2016-07-19 | Dragados | Foundation works start ("acta de replanteo") | 2016-11-18 | ICRR/IAC | Requested license for mechanical installation | 2017-01-11 | Dragados | Foundation works finish | 2017-06-14 | Garafia | Town hall of Garafia issues license for mechanical installation |