* Jul. 22th: A problem in the Flywheel PLC prevented to park out the telescope (lost connection with PLC). Because of this trouble, we could not operate the telescope this day. Jul. 23th: By Koji's instruction from remote, we unplugged the power cable of the PLC and replugged. Then, the PLC is back online. For more detail, see [http://www.lst1.iac.es/elog/ENERGY/32 ENERGY#32] | * Jul. 22th: A problem in the Flywheel PLC prevented to park out the telescope (lost connection with PLC). Because of this trouble, we could not operate the telescope this day. Jul. 23th: By Koji's instruction from remote, we unplugged the power cable of the PLC and replugged. Then, the PLC is back online. For more detail, see [http://www.lst1.iac.es/elog/ENERGY/32 ENERGY#32] | ||
* Jul. 23th - 25th: Two Schneider engineers worked on a cooling unit for IT container and they fixed it. Now 2 out of 3 units are available | * Jul. 23th - 25th: Two Schneider engineers worked on a cooling unit for IT container and they fixed it. Now 2 out of 3 units are available | ||
* Jul. 24th: Dragados put gravel in the south east side of the telescope area | * Jul. 24th: Dragados put gravel in the south east side of the telescope area | ||
− | * Jul. 26th: GUI | + | * Jul. 26th: Drive GUI stuck due to a wrong shutdown procedure (a human error, access tower&CSS statuses were not properly checked before entering the telescope area) For more detail, see [http://www.lst1.iac.es/elog/DRIVE/269 DRIVE#269] |
* Jul. 27th: Visit of AMANAR from Morocco (14 kids + 16 adults), fully satisfied | * Jul. 27th: Visit of AMANAR from Morocco (14 kids + 16 adults), fully satisfied | ||
* Pointing: | * Pointing: | ||
− | ** New Az offset value was derived by Satoshi | + | ** New Az offset value (0.57) was derived by Satoshi |
− | ** Strange PSF spot shift when the | + | ** Strange PSF spot shift when the telescope passes Az of both 0 deg and 180 deg. Ongoing discussion between Drive and Optics experts |
* AMCs: Sometimes PC4 needed to reboot | * AMCs: Sometimes PC4 needed to reboot | ||
* Camera (CaCo, EvB): | * Camera (CaCo, EvB): | ||
Line 26: | Line 26: | ||
** Protection to prevent movement of SIS was implemented (Zd <90 deg) | ** Protection to prevent movement of SIS was implemented (Zd <90 deg) | ||
** Protection of enabling HV for front light | ** Protection of enabling HV for front light | ||
− | |||
** New EvB v3 was installed and working well at high rate (>15 kHz) | ** New EvB v3 was installed and working well at high rate (>15 kHz) | ||
** GPS was not receiving -> Reboot -> Work fine (receiver and DHCP working) | ** GPS was not receiving -> Reboot -> Work fine (receiver and DHCP working) |
Revision as of 09:31, 8 August 2019
Go back to Logbook Commissioning
P14 (19.7.2019 - 5.8.2019)
- Commissioning Shift Period: 14
- Dates: 19.7.2019 - 5.8.2019
- Commissioning Shift Leader: Yusuke Suda
- Commissioning Shifters / Experts:
- Drive: shift crew
- Camera: Mitsunari Takahashi (until 23.7), Daniel Kerszberg (from 22.7), Juan Abel Barrio (22.7 - 2.8), Julien Houles (23.7 - 1.8)
- AMC / Mirrors: Satoshi Fukami, Tomohiro Inada, Yoshiki Ohtani (from 22.7)
Summary
- Jul. 22th: A problem in the Flywheel PLC prevented to park out the telescope (lost connection with PLC). Because of this trouble, we could not operate the telescope this day. Jul. 23th: By Koji's instruction from remote, we unplugged the power cable of the PLC and replugged. Then, the PLC is back online. For more detail, see ENERGY#32
- Jul. 23th - 25th: Two Schneider engineers worked on a cooling unit for IT container and they fixed it. Now 2 out of 3 units are available
- Jul. 24th: Dragados put gravel in the south east side of the telescope area
- Jul. 26th: Drive GUI stuck due to a wrong shutdown procedure (a human error, access tower&CSS statuses were not properly checked before entering the telescope area) For more detail, see DRIVE#269
- Jul. 27th: Visit of AMANAR from Morocco (14 kids + 16 adults), fully satisfied
- Pointing:
- New Az offset value (0.57) was derived by Satoshi
- Strange PSF spot shift when the telescope passes Az of both 0 deg and 180 deg. Ongoing discussion between Drive and Optics experts
- AMCs: Sometimes PC4 needed to reboot
- Camera (CaCo, EvB):
- Module blocked at high rate (>15 kHz) fixed
- SIS became operable again
- Protection to prevent movement of SIS was implemented (Zd <90 deg)
- Protection of enabling HV for front light
- New EvB v3 was installed and working well at high rate (>15 kHz)
- GPS was not receiving -> Reboot -> Work fine (receiver and DHCP working)
- We took rate scans, pedestal and flatfield runs
- We could take test shower data (with SIS, pointing to a bright star)