Difference between revisions of "Logbook Camera-Assembly"

From my_wiki
Jump to: navigation, search
(Enter comments in reverse time order)
(Enter comments in reverse time order)
Line 6: Line 6:
 
|- valign="top"
 
|- valign="top"
  
 +
|-
 +
| 2018-05-02 || Oscar Blanch, Laia Cardiel,  || Optical fiber for the slow control has been connected both inside the camera and outside from the patch panel to an external switch.
 +
MAES came and the relay problem was solved by adjusting the potentiometer. Figure 1 shows the current configuration, which does not trigger the relay to go down. It has been operating for already 30 minutes.
 +
 +
||
 +
 +
|| [https://drive.google.com/open?id=1GuXU4bXMW6Iem5H8M0HUC10Y8Re_fF267AJWt-pFXcI drive]
 
|-
 
|-
 
| 2018-05-01 || Nadia Fouque, Jean-Luc Panazol, Oscar Blanch, Merve Colak, Daniel Kerszberg  || ECC set up to have same state than in CIEMAT
 
| 2018-05-01 || Nadia Fouque, Jean-Luc Panazol, Oscar Blanch, Merve Colak, Daniel Kerszberg  || ECC set up to have same state than in CIEMAT
Line 14: Line 21:
 
Run Main-ECC.exe all night without problem.
 
Run Main-ECC.exe all night without problem.
  
  || [https://docs.google.com/document/d/1iG9-bpzXUlAjfKS69DB3mKXPRFIo6jXzGbSdiqpq31s/edit drive]
+
  || [https://docs.google.com/document/d/1iG9-bpzXUlAjfKS69DB3mKXPRFIo6jXzGbSdiqpq31s/edit?usp=sharing drive]
 
|-
 
|-
 
| 2018-04-27 || Javier G., Carlos Díaz, Miguel Polo, Laia Cardiel, Otger Ballester, Sebastian Grinspun, Oscar Blanch, Merve Colak, Daniel Kerszberg  || Camera arrived at IFAE from CIEMAT
 
| 2018-04-27 || Javier G., Carlos Díaz, Miguel Polo, Laia Cardiel, Otger Ballester, Sebastian Grinspun, Oscar Blanch, Merve Colak, Daniel Kerszberg  || Camera arrived at IFAE from CIEMAT

Revision as of 16:48, 2 May 2018

Enter comments in reverse time order

Date Who did it? Action Comments Documents
2018-05-02 Oscar Blanch, Laia Cardiel, Optical fiber for the slow control has been connected both inside the camera and outside from the patch panel to an external switch.

MAES came and the relay problem was solved by adjusting the potentiometer. Figure 1 shows the current configuration, which does not trigger the relay to go down. It has been operating for already 30 minutes.

drive
2018-05-01 Nadia Fouque, Jean-Luc Panazol, Oscar Blanch, Merve Colak, Daniel Kerszberg ECC set up to have same state than in CIEMAT

Control of the PDB with standalone labview ⇒ OK. Control of the ECC state machine with the Main ECC program ⇒ OK. Installation of the Main ECC executable into the cRIO ⇒ OK. Run Main-ECC.exe all night without problem.

drive
2018-04-27 Javier G., Carlos Díaz, Miguel Polo, Laia Cardiel, Otger Ballester, Sebastian Grinspun, Oscar Blanch, Merve Colak, Daniel Kerszberg Camera arrived at IFAE from CIEMAT Camera was unload and introduced in the shielded room

Together with the camera, the chiller (as well as pipes) and the hydraulic system to open frontal door arrived to IFAE. Carlos Díaz and Miguel Polo open the back door of the camera. 3-Phase and 1-Phase power connected to the camera Ethernet RJ45 cable connected to main switch inside the camera long enough to be connected to a computer outside the shielded room (See Picture 4) which will be needed for ECC validation from May 1st to May 3rd.

drive
2018-04-25 Javi Gaweda, Noel Space around the Shielded Room is prepared for the camera arrival;

Wall of the shielded room open to allow to enter the camera.

drive
2018-04-24 Quim, Elena, Daniel, Quentin and Lea Clean shielded room drive
2018-04-23 Léa, Quentin, Elena Dark-Box external setup of 2 modules drive
2018-04-20 Dirk Hoffmann, Julien Houles, Quim drive
2018-04-19 Dirk Hoffmann, Julien Houles, Oscar Blanch, Takayuki Saito Received TIB (+ power cable) drive
2018-04-18 Léa, Dirk, Julien, Elena, Joan drive
2018-04-17 Cristobal, Quim, Léa, Julien IFAE switch replaced from Marseille's one drive
2018-04-16 Lea, Quim & Cristobal Taka visits IFAE.

Fiber-switch connected.

drive
2018-04-13 Camilla, Lea, Quim & Oscar

Power connection mounted and tested. Communication with 10 modules checked.

drive
2018-04-12 Camilla, Lea, Quim & Oscar Vertical bus bar arrived;

Problem with the plugs cable from the bus bar to the back plane; Joan and Alex are building new cable (cables have been plugged manually and fixed with tape by Lea&Quim); Mezzanines attached; 3-phase power supply wired, but not yet plugged;

drive
2018-04-11

Camilla, Lea, Quim & Oscar

The set up for 10 modules is organized; Larger switch (to allow for 10 modules); 1 3-phase power supply (2 spares) but not yet wired; drive