Difference between revisions of "Logbook Camera-Assembly"
(→Enter comments in reverse time order) |
(→Enter comments in reverse time order) |
||
Line 10: | Line 10: | ||
|| | || | ||
** ECC actvities: | ** ECC actvities: | ||
− | * Shutter tests, use Carlos Standalone program, Shutter Open and Close correctly; | + | * Shutter tests, use Carlos Standalone program, Shutter Open and Close correctly; |
− | * Shutter program will be included in next ECC version program. | + | * Shutter program will be included in next ECC version program. |
** Accessing camera front: | ** Accessing camera front: | ||
− | * Three module racks are now outside the shielded room to allow the frontal door to be opened; | + | * Three module racks are now outside the shielded room to allow the frontal door to be opened; |
− | * Camera was moved inside the multitool to be able to open the frontal door, the hydraulic system was mounted (Figure 1) and the door was open (Figure 2), when leaving the door was left close; | + | * Camera was moved inside the multitool to be able to open the frontal door, the hydraulic system was mounted (Figure 1) and the door was open (Figure 2), when leaving the door was left close; |
− | * Shutter was open successfully, when leaving the shutter was left close, it needs standalone labview program to run for the moment. | + | * Shutter was open successfully, when leaving the shutter was left close, it needs standalone labview program to run for the moment. |
** Module validation before and after installation: | ** Module validation before and after installation: | ||
− | * Working on modified IAC test; | + | * Working on modified IAC test; |
− | * Two modules set-up for validation before installing in the camera: read temperatures, set some registers and check correctly done, L0 and L1 rate scans as well as short run with {HV and Pulse Injection off, Pulse Injection on, HV on}; | + | * Two modules set-up for validation before installing in the camera: read temperatures, set some registers and check correctly done, L0 and L1 rate scans as well as short run with {HV and Pulse Injection off, Pulse Injection on, HV on}; |
− | * For validation in the camera (every ~30 modules installed), we add rate scans and runs with flasher. | + | * For validation in the camera (every ~30 modules installed), we add rate scans and runs with flasher. |
** Preparing chiller installation: | ** Preparing chiller installation: | ||
− | * Chiller connected to power; | + | * Chiller connected to power; |
− | * Water pipes pre-installed; | + | * Water pipes pre-installed; |
− | * Water to fill the chiller available. | + | * Water to fill the chiller available. |
Revision as of 06:51, 4 May 2018
Enter comments in reverse time order
Date | Who did it? | Action | Comments | Documents |
---|---|---|---|---|
2018-05-03 | Nadia Fouque, Carlos Díaz, Miguel Polo, Antonio López, Seiya Nozaki, Oscar Blanch, Laia Cardiel, Javi Gaweda, Juan Boix, | ECC activities, Accessing camera front, Module validation before installation |
* Shutter tests, use Carlos Standalone program, Shutter Open and Close correctly; * Shutter program will be included in next ECC version program.
* Three module racks are now outside the shielded room to allow the frontal door to be opened; * Camera was moved inside the multitool to be able to open the frontal door, the hydraulic system was mounted (Figure 1) and the door was open (Figure 2), when leaving the door was left close; * Shutter was open successfully, when leaving the shutter was left close, it needs standalone labview program to run for the moment.
* Working on modified IAC test; * Two modules set-up for validation before installing in the camera: read temperatures, set some registers and check correctly done, L0 and L1 rate scans as well as short run with {HV and Pulse Injection off, Pulse Injection on, HV on}; * For validation in the camera (every ~30 modules installed), we add rate scans and runs with flasher.
* Chiller connected to power; * Water pipes pre-installed; * Water to fill the chiller available.
|
drive |
2018-05-02 | Oscar Blanch, Laia Cardiel, Nadia Fouque, Jean Luc Panazol, Daniel Kerszberg, |
Validation of ECC already using executable in CRIO |
|
drive |
2018-05-01 | Nadia Fouque, Jean-Luc Panazol, Oscar Blanch, Merve Colak, Daniel Kerszberg | ECC set up to have same state than in CIEMAT |
Control of the PDB with standalone labview ⇒ OK. Control of the ECC state machine with the Main ECC program ⇒ OK. Installation of the Main ECC executable into the cRIO ⇒ OK. Run Main-ECC.exe all night without problem. |
drive |
2018-04-27 | Javier G., Carlos Díaz, Miguel Polo, Laia Cardiel, Otger Ballester, Sebastian Grinspun, Oscar Blanch, Merve Colak, Daniel Kerszberg | Camera arrived at IFAE from CIEMAT | Camera was unload and introduced in the shielded room
Together with the camera, the chiller (as well as pipes) and the hydraulic system to open frontal door arrived to IFAE. Carlos Díaz and Miguel Polo open the back door of the camera. 3-Phase and 1-Phase power connected to the camera Ethernet RJ45 cable connected to main switch inside the camera long enough to be connected to a computer outside the shielded room (See Picture 4) which will be needed for ECC validation from May 1st to May 3rd. |
drive |
2018-04-25 | Javi Gaweda, Noel | Space around the Shielded Room is prepared for the camera arrival;
Wall of the shielded room open to allow to enter the camera. |
drive | |
2018-04-24 | Quim, Elena, Daniel, Quentin and Lea | Clean shielded room | drive | |
2018-04-23 | Léa, Quentin, Elena | Dark-Box external setup of 2 modules | drive | |
2018-04-20 | Dirk Hoffmann, Julien Houles, Quim | drive | ||
2018-04-19 | Dirk Hoffmann, Julien Houles, Oscar Blanch, Takayuki Saito | Received TIB (+ power cable) | drive | |
2018-04-18 | Léa, Dirk, Julien, Elena, Joan | drive | ||
2018-04-17 | Cristobal, Quim, Léa, Julien | IFAE switch replaced from Marseille's one | drive | |
2018-04-16 | Lea, Quim & Cristobal | Taka visits IFAE.
Fiber-switch connected. |
drive | |
2018-04-13 | Camilla, Lea, Quim & Oscar |
Power connection mounted and tested. Communication with 10 modules checked. |
drive | |
2018-04-12 | Camilla, Lea, Quim & Oscar | Vertical bus bar arrived |
Problem with the plugs cable from the bus bar to the back plane; Joan and Alex are building new cable (cables have been plugged manually and fixed with tape by Lea&Quim); Mezzanines attached; 3-phase power supply wired, but not yet plugged; |
drive |
2018-04-11 |
Camilla, Lea, Quim & Oscar |
The set up for 10 modules is organized; Larger switch (to allow for 10 modules); 1 3-phase power supply (2 spares) but not yet wired; | drive |