== Tentative plans 2019 ==
+
== Overall Plans 2019 ==
 
* CW 12: Camera tests, mainly calibration. No optics tests planned, no drive tests planned. MPI team will come to make improvements in the mechanics
 
* CW 12: Camera tests, mainly calibration. No optics tests planned, no drive tests planned. MPI team will come to make improvements in the mechanics
 
* CW 13: LAPP team is back, drive tests. Dirk and Julien: DAQ tests. Still unclear if the mirrors will be uncovered or not, depends how the next week goes. <br> Toni Dettlaff will do some optics work inside the dish, also some work in the commissioning container
 
* CW 13: LAPP team is back, drive tests. Dirk and Julien: DAQ tests. Still unclear if the mirrors will be uncovered or not, depends how the next week goes. <br> Toni Dettlaff will do some optics work inside the dish, also some work in the commissioning container

Revision as of 16:06, 11 March 2019

Instructions and useful links for the LST commissioning leaders


LST1 Commissioning Leaders

Shifters 2019

Overall Plans 2019

  • CW 12: Camera tests, mainly calibration. No optics tests planned, no drive tests planned. MPI team will come to make improvements in the mechanics
  • CW 13: LAPP team is back, drive tests. Dirk and Julien: DAQ tests. Still unclear if the mirrors will be uncovered or not, depends how the next week goes.
    Toni Dettlaff will do some optics work inside the dish, also some work in the commissioning container