Difference between revisions of "Commissioning Shift P14"
Yusuke Suda (talk | contribs) |
Yusuke Suda (talk | contribs) |
||
Line 1: | Line 1: | ||
− | Go back to [http://www.lst1.iac.es/wiki/index.php/Logbook_Commissioning | + | Go back to [http://www.lst1.iac.es/wiki/index.php/Logbook_Commissioning Logbook Commissioning] |
= [[Commissioning_Shift_P14|P14 (19.7.2019 - 5.8.2019)]] = | = [[Commissioning_Shift_P14|P14 (19.7.2019 - 5.8.2019)]] = | ||
Line 8: | Line 8: | ||
* Commissioning Shifters / Experts: | * Commissioning Shifters / Experts: | ||
** Drive: shift crew | ** Drive: shift crew | ||
− | ** Camera: Mitsunari Takahashi (until 23.7), Daniel Kerszberg, Juan Abel Barrio ( | + | ** Camera: Mitsunari Takahashi (until 23.7), Daniel Kerszberg (from 22.7), Juan Abel Barrio (22.7 - 2.8), Julien Houles (23.7 - 1.8) |
− | ** AMC / Mirrors: Satoshi Fukami, Tomohiro Inada, Yoshiki Ohtani | + | ** AMC / Mirrors: Satoshi Fukami, Tomohiro Inada, Yoshiki Ohtani (from 22.7) |
− | ** | + | |
+ | = [[Summary]] = | ||
+ | * Jul. 22th: A problem in the Flywheel PLC prevented to park out the telescope (lost connection with PLC). Because of this trouble, we could not operate the telescope this day. Jul. 23th: With Koji's instruction from remote, we unplugged the power cable of the PLC and replugged. Then, the PLC was back. For more detail, see [http://www.lst1.iac.es/elog/ENERGY/32 ENERGY#32] | ||
+ | * Jul. 23th - 25th: Two Schneider engineers worked on a cooling unit for IT container and they fixed it. Now 2 out of 3 units are available | ||
+ | * Jul. 24th: Dragados put gravel in the south east side of the telescope area | ||
+ | * Jul. 26th: GUI stacked due to a wrong shutdown procedure (a human error, access tower&CSS statuses were not properly checked before entering the telescope area) For more detail, see [http://www.lst1.iac.es/elog/DRIVE/269 DRIVE#269] | ||
+ | * Jul. 27th: Visit of AMANAR from Morocco (14 kids + 16 adults), fully satisfied | ||
+ | * Pointing: | ||
+ | ** New Az offset value was derived by Satoshi | ||
+ | ** Strange PSF spot shift when the tel. passes Az of 0 deg. Ongoing discussion between Drive and Optics experts | ||
+ | * AMCs: Sometimes PC4 needed to reboot | ||
+ | * Camera (CaCo, EvB): | ||
+ | ** Module blocked at high rate (>15 kHz) fixed | ||
+ | ** SIS became operable again | ||
+ | ** Protection to prevent movement of SIS was implemented (Zd <90 deg) | ||
+ | ** Protection of enabling HV for front light | ||
+ | ** Stable version of CaCo by Friday with minor modifications | ||
+ | ** New EvB v3 was installed and working well at high rate (>15 kHz) | ||
+ | ** GPS was not receiving -> Reboot -> Work fine (receiver and DHCP working) | ||
+ | ** We took rate scans, pedestal and flatfield runs | ||
+ | ** We could take test shower data (with SIS, pointing to a bright star) | ||
+ | |||
+ | = [[Commissioning shift reports]] = |
Revision as of 09:26, 8 August 2019
Go back to Logbook Commissioning
P14 (19.7.2019 - 5.8.2019)
- Commissioning Shift Period: 14
- Dates: 19.7.2019 - 5.8.2019
- Commissioning Shift Leader: Yusuke Suda
- Commissioning Shifters / Experts:
- Drive: shift crew
- Camera: Mitsunari Takahashi (until 23.7), Daniel Kerszberg (from 22.7), Juan Abel Barrio (22.7 - 2.8), Julien Houles (23.7 - 1.8)
- AMC / Mirrors: Satoshi Fukami, Tomohiro Inada, Yoshiki Ohtani (from 22.7)
Summary
- Jul. 22th: A problem in the Flywheel PLC prevented to park out the telescope (lost connection with PLC). Because of this trouble, we could not operate the telescope this day. Jul. 23th: With Koji's instruction from remote, we unplugged the power cable of the PLC and replugged. Then, the PLC was back. For more detail, see ENERGY#32
- Jul. 23th - 25th: Two Schneider engineers worked on a cooling unit for IT container and they fixed it. Now 2 out of 3 units are available
- Jul. 24th: Dragados put gravel in the south east side of the telescope area
- Jul. 26th: GUI stacked due to a wrong shutdown procedure (a human error, access tower&CSS statuses were not properly checked before entering the telescope area) For more detail, see DRIVE#269
- Jul. 27th: Visit of AMANAR from Morocco (14 kids + 16 adults), fully satisfied
- Pointing:
- New Az offset value was derived by Satoshi
- Strange PSF spot shift when the tel. passes Az of 0 deg. Ongoing discussion between Drive and Optics experts
- AMCs: Sometimes PC4 needed to reboot
- Camera (CaCo, EvB):
- Module blocked at high rate (>15 kHz) fixed
- SIS became operable again
- Protection to prevent movement of SIS was implemented (Zd <90 deg)
- Protection of enabling HV for front light
- Stable version of CaCo by Friday with minor modifications
- New EvB v3 was installed and working well at high rate (>15 kHz)
- GPS was not receiving -> Reboot -> Work fine (receiver and DHCP working)
- We took rate scans, pedestal and flatfield runs
- We could take test shower data (with SIS, pointing to a bright star)