Difference between revisions of "Commissioning Shift P16"

From my_wiki
Jump to: navigation, search
m
m
 
Line 23: Line 23:
 
*Camera (CaCo, EvB):
 
*Camera (CaCo, EvB):
 
**16/08/19 - Fallout from the network restructuring continues.  
 
**16/08/19 - Fallout from the network restructuring continues.  
 +
 +
**17/08/19 - Fallout from the network restructuring continues. Issue possibly narrowed to down to TIB. 
  
  
Line 29: Line 31:
 
**16/08/19 - Starguider installed.  Planning tests on Monday.
 
**16/08/19 - Starguider installed.  Planning tests on Monday.
 
**16/08/19 - TCU testing continues.
 
**16/08/19 - TCU testing continues.
 +
 +
**17/08/19 - Additional webcams installed for ALS East, ALS West, West Tower to Camera Platform, and Elevation Bolt.  Still need to forward signal through IT container in order to see in CC. 
  
 
*Problems and Visits:
 
*Problems and Visits:

Latest revision as of 13:53, 18 August 2019

P16 (16.8.2019 - 2.9.2019)[edit]

  • Commissioning Shift Period: 16
  • Dates: 16.8.2019 - 2.9.2019
  • Commissioning Shift Leader: David Green
  • Commissioning Shifters / Experts:
    • Drive: Paolo Calisee (19/08 - 31/08), shift crew
    • Camera: Yoshiki Ohtani (till 02/09), Elena Moretti (21/08 - 04/09)
    • AMC / Mirrors:

Summary[edit]

  • Drive:


  • Pointing:


  • AMC:


  • Camera (CaCo, EvB):
    • 16/08/19 - Fallout from the network restructuring continues.
    • 17/08/19 - Fallout from the network restructuring continues. Issue possibly narrowed to down to TIB.


  • Other:
    • 16/08/19 - Fallout from the network restructuring continues.
    • 16/08/19 - Starguider installed. Planning tests on Monday.
    • 16/08/19 - TCU testing continues.
    • 17/08/19 - Additional webcams installed for ALS East, ALS West, West Tower to Camera Platform, and Elevation Bolt. Still need to forward signal through IT container in order to see in CC.
  • Problems and Visits:
    • August 16th, Open Day for Garafia. Done.

Commissioning shift reports[edit]