Difference between revisions of "Logbook Permissions"
(→Enter comments in reverse time order) |
(→Enter comments in reverse time order) |
||
Line 13: | Line 13: | ||
| 2016-07-19 || Dragados || Foundation works start ("acta de replanteo") || || | | 2016-07-19 || Dragados || Foundation works start ("acta de replanteo") || || | ||
|- valign="top" | |- valign="top" | ||
− | | 2016-07-25 || Garafia || Town hall of Garafia requests | + | | 2016-07-25 || Garafia || Town hall of Garafia requests license for mechanical installation || || |
+ | |- valign="top" | ||
+ | | 2016-06-15 || IFAE || Paid foundation license fee || Total cost 31500 € || | ||
|- valign="top" | |- valign="top" | ||
| 2016-05-11 || Garafia || Town hall of Garafia issues second step of license for foundation|| || | | 2016-05-11 || Garafia || Town hall of Garafia issues second step of license for foundation|| || | ||
Line 21: | Line 23: | ||
| 2015-12-11 || IAC || Tender for foundation published (in Spanish BOE) || || | | 2015-12-11 || IAC || Tender for foundation published (in Spanish BOE) || || | ||
|- valign="top" | |- valign="top" | ||
+ | | 2015-11-10 || Architect || Requested second step of license for foundation || Paid 2% of estimated license tax || | ||
| 2015-11-09 || Architect's association || La Palma architect's official association accepts final foundation drawings ("project") || || | | 2015-11-09 || Architect's association || La Palma architect's official association accepts final foundation drawings ("project") || || | ||
|- valign="top" | |- valign="top" | ||
Line 31: | Line 34: | ||
| 2015-01-15 || Icinco || Company Icinco delivers geotechnical study || || | | 2015-01-15 || Icinco || Company Icinco delivers geotechnical study || || | ||
|- valign="top" | |- valign="top" | ||
− | | 2014-11-15 || IFAE (Cortina) || Company Icinco hired for geotechnical study || | + | | 2014-11-15 || IFAE (Cortina) || Company Icinco hired for geotechnical study || Paid full cost 3600 € (incl. IGIC) || |
|- valign="top" | |- valign="top" | ||
− | | 2014-12-15 || IFAE (Cortina) || Contract between IFAE and architect signed || | + | | 2014-12-15 || IFAE (Cortina) || Contract between IFAE and architect signed || Paid half of cost (12000 € net) || |
|- valign="top" | |- valign="top" | ||
| 2014-10-01 || IFAE (Cortina) || Started bidding to hire foundation architect || || | | 2014-10-01 || IFAE (Cortina) || Started bidding to hire foundation architect || || |
Revision as of 09:54, 7 September 2017
Enter comments in reverse time order
Date | Who did it? | Action | Comments | Documents | |||||
---|---|---|---|---|---|---|---|---|---|
2017-06-14 | Garafia | Town hall of Garafia issues license for mechanical installation | |||||||
2017-01-11 | Dragados | Foundation works finish | |||||||
2016-11-18 | ICRR/IAC | Requested license for mechanical installation | |||||||
2016-07-19 | Dragados | Foundation works start ("acta de replanteo") | |||||||
2016-07-25 | Garafia | Town hall of Garafia requests license for mechanical installation | |||||||
2016-06-15 | IFAE | Paid foundation license fee | Total cost 31500 € | ||||||
2016-05-11 | Garafia | Town hall of Garafia issues second step of license for foundation | |||||||
2016-05-10 | IAC | Tender finishes. Company Dragados selected | |||||||
2015-12-11 | IAC | Tender for foundation published (in Spanish BOE) | |||||||
2015-11-10 | Architect | Requested second step of license for foundation | Paid 2% of estimated license tax | 2015-11-09 | Architect's association | La Palma architect's official association accepts final foundation drawings ("project") | |||
2015-10-22 | Cabildo | Cabildo issues first step of license for foundation | |||||||
2015-03-16 | IFAE/Architect | Request first step of license for foundation ("recalificación") | |||||||
2015-03-15 | Architect (Estudio AT3) | Foundation preliminary drawings ("pre-project"), including environmental study, finished | |||||||
2015-01-15 | Icinco | Company Icinco delivers geotechnical study | |||||||
2014-11-15 | IFAE (Cortina) | Company Icinco hired for geotechnical study | Paid full cost 3600 € (incl. IGIC) | ||||||
2014-12-15 | IFAE (Cortina) | Contract between IFAE and architect signed | Paid half of cost (12000 € net) | ||||||
2014-10-01 | IFAE (Cortina) | Started bidding to hire foundation architect |