Logbook Camera-Assembly
Enter comments in reverse time order
Date | Who did it? | Action | Comments | Documents |
---|---|---|---|---|
2018-05-02 | Oscar Blanch, Laia Cardiel, Nadia Fouque, Jean Luc Panazol, Daniel Kerszberg, |
Validation of ECC already using executable in CRIO |
|
drive |
2018-05-01 | Nadia Fouque, Jean-Luc Panazol, Oscar Blanch, Merve Colak, Daniel Kerszberg | ECC set up to have same state than in CIEMAT |
Control of the PDB with standalone labview ⇒ OK. Control of the ECC state machine with the Main ECC program ⇒ OK. Installation of the Main ECC executable into the cRIO ⇒ OK. Run Main-ECC.exe all night without problem. |
drive |
2018-04-27 | Javier G., Carlos Díaz, Miguel Polo, Laia Cardiel, Otger Ballester, Sebastian Grinspun, Oscar Blanch, Merve Colak, Daniel Kerszberg | Camera arrived at IFAE from CIEMAT | Camera was unload and introduced in the shielded room
Together with the camera, the chiller (as well as pipes) and the hydraulic system to open frontal door arrived to IFAE. Carlos Díaz and Miguel Polo open the back door of the camera. 3-Phase and 1-Phase power connected to the camera Ethernet RJ45 cable connected to main switch inside the camera long enough to be connected to a computer outside the shielded room (See Picture 4) which will be needed for ECC validation from May 1st to May 3rd. |
drive |
2018-04-25 | Javi Gaweda, Noel | Space around the Shielded Room is prepared for the camera arrival;
Wall of the shielded room open to allow to enter the camera. |
drive | |
2018-04-24 | Quim, Elena, Daniel, Quentin and Lea | Clean shielded room | drive | |
2018-04-23 | Léa, Quentin, Elena | Dark-Box external setup of 2 modules | drive | |
2018-04-20 | Dirk Hoffmann, Julien Houles, Quim | drive | ||
2018-04-19 | Dirk Hoffmann, Julien Houles, Oscar Blanch, Takayuki Saito | Received TIB (+ power cable) | drive | |
2018-04-18 | Léa, Dirk, Julien, Elena, Joan | drive | ||
2018-04-17 | Cristobal, Quim, Léa, Julien | IFAE switch replaced from Marseille's one | drive | |
2018-04-16 | Lea, Quim & Cristobal | Taka visits IFAE.
Fiber-switch connected. |
drive | |
2018-04-13 | Camilla, Lea, Quim & Oscar |
Power connection mounted and tested. Communication with 10 modules checked. |
drive | |
2018-04-12 | Camilla, Lea, Quim & Oscar | Vertical bus bar arrived |
Problem with the plugs cable from the bus bar to the back plane; Joan and Alex are building new cable (cables have been plugged manually and fixed with tape by Lea&Quim); Mezzanines attached; 3-phase power supply wired, but not yet plugged; |
drive |
2018-04-11 |
Camilla, Lea, Quim & Oscar |
The set up for 10 modules is organized; Larger switch (to allow for 10 modules); 1 3-phase power supply (2 spares) but not yet wired; | drive |