Date |
Who did it? |
Action |
Comments |
Documents
|
2018-06-08 |
Tomo, Patricia, Darga |
Empty crates transportation |
Today we finished to transport 8 empty crates from the site to Roque. |
|
2018-05-23 |
Toni, Satoshi, Yusuke, CaSana |
Mirror Installation |
Today we finished to install 10 mirrors on the structure (in total 181) and we finished all we can do so far. We found one camera which doesn't have its connector shielded nor 4 small clamping pieces of its holder. We found a suitable plastic bag for the shield, and we temporarily stole the small pieces from a CMOS holder on site. There are still 6 crates behind the telescope. |
|
2018-05-21 |
Yusuke, Satoshi, Taku, Darga Express |
Mirror Transportation |
Today we successfully brought 20 mirrors (4 crates) from Mirca to Roque, distributed them at Roque putting crate covers, brought 9 empty crates from Roque to Mirca and distributed them in Mirca. |
|
2018-05-18 |
Toni, Satoshi, Yusuke, CaSana |
Mirror Installation |
Today we finished to install 10 mirrors on the structure (in total 171) and we finished all we can do so far. Casana people attached all the IF plates except "special special IF plates" and ones of y=+9 which should not be installed before CSS installation according to LAPP people. CaSana also rotated the structure to the north. |
|
2018-05-17 |
Toni, Satoshi, Yusuke, CaSana |
Mirror Installation |
Today we finished to install 22 mirrors on the structure (in total 161). Casana people have installed most of the "normal special IF plates" except ones with y=+9. |
|
2018-05-15 |
Tomohiro, Toni, Satoshi, Yusuke, Taku, CaSana |
Mirror Installation |
Today we finished to install 16 mirrors on the structure (in total 139). We prepared all special interface plates. Casana people will install them tomorrow.
|
|
2018-05-11 |
Koji, Tomohiro, Toni, CaSana |
Mirror Installation |
Today we finished to install 24 mirrors on the structure (in total 123). In the middle of the installation, we hit the bottom edge of a mirror to the bottom of the cradle. It made a small crack(1cm×1cm) on the surface of the mirror. We installed it after we put the silicone for repairing. It is located in (-4,-6) After we hit the mirror to the bottom of the cradle, we put the soft material to that region for protecting a surface of mirrors.
|
|
2018-05-10 |
Koji, Tomohiro, Toni, CaSana |
Mirror Transportation & Installation |
Today we brought 40 mirrors again, and then we finished to install 13 mirrors on the structure (in total 99 and replaced the broken one to new one which we brought yesterday.
|
|
2018-05-09 |
Koji, Tomohiro, CaSana |
Mirror Transportation |
Today we brought 40 mirrors (8 crates) from Mirca to Roque by Darga Express successfully and we also brought 8 empty crates back to Mirca. CaSana installed several special IF plates.
|
2018-05-08 |
Koji, Tomohiro, Toni, Casana |
Mirror Installation |
We finished to install 12 mirrors on the structure (in total 86). We also installed the 4 special interface plates in the left bottom part, so we could install mirrors at those points. There was one accident. When the CaSana people were installing the mirror in (2, -8), they found a crack on the surface of the mirror in (0,-8). Probably they made it, because they had tried to get their cherry picker closer to the mirror many times. The size of crack is about 1cm×4cm from their pictures and movies. We asked Uwe to put silicone on the surface of the cracked mirror as a temporal solution and they did. Probably we will replace that mirror to new one at Mirca as soon as possible.
|
|
2018-05-04 |
Koji, Tomohiro, Casana |
Mirror Installation |
We finished to install 16 mirrors on the structure (in total 74).
|
|
2018-05-03 |
Koji, Tomohiro, Casana |
Mirror Installation |
We finished to install 14 mirrors on the structure (in total 58). We found one CMOS camera whose mirror was already installed last time. Its coordinate is (+1,+3). After we found it, we asked Uwe(CaSana) to change wrong one to correct one for the mirror in (+1,+3) and they did successfully. They told us that the mirror in (+1,+3) was with the CMOS camera for (1,-3) mistakenly. |
|
2018-04-28 |
Satoshi, Tomohiro, Casana |
Mirror Installation |
We finished to install 12 mirrors on the structure (in total 44). Casana people inside the dish dropped one O-ring while removing actuator caps. Once by mistake we assembled a wrong combination of a CMOS and a mirror. We noticed that when we were putting the assembled one on the cradle. We should always be careful for the combination. |
|
2018-04-27 |
Martin, Satoshi, Tomohiro, Casana |
Mirror Installation |
We finished to install 16 mirrors on the structure (in total 32). Casana people inside the dish dropped a hexagonal key. It was later found on the catwalk below them. We were not sure if people inside the dish unscrew milling parts to straighten actuators and fix the milling parts again. Martin went inside the dish and checked that they are doing these works for all the mirrors. |
|
2018-04-26 |
Martin, Satoshi, Tomohiro, Casana |
Mirror Installation |
We started the mirror installation at Roque. We finished to install 15 mirrors on the structure (in total 16). |
|