Date |
Who did it? |
Action |
Comments |
Documents
|
2018-08-21 |
Toni, Dragados |
AMC Box cabling |
We finished today internal cabling of 2 boxes (2,5). Till now we finished already 14 AMC Boxes. One of the Dragados workers still has failed due to illness today and one of the two other helpers arrived shortly after noon. |
|
2018-08-20 |
Toni, Dragados |
AMC Box cabling |
We finished today internal cabling of 3 boxes (6,4,3). One of the Dragados workers still has failed due to illness today. We are thus only three with me for the wiring. !!! Today I found an actuator (Mirror -7,+7) where one of its three springs does not fit snugly against the lid of the actuator. Please check the pictuare. !!! |
|
|
2018-08-17 |
Toni, Dragados |
AMC Box cabling |
We finished today internal cabling of 2 boxes (9,8). One of the Dragados workers still has failed due to illness today. We are thus only three with me for the wiring. |
|
|
2018-08-16 |
Toni, Casana |
Replace of broken mirror -5, -5 |
Broken mirror -5, -5 has been replaced with a spare mirror -5, -5. |
|
Toni, Dragados |
AMC Box cabling |
We finished today internal cabling of 3 boxes (C,7,4). One of the Dragados workers has failed due to illness today. We are thus only three with me for the wiring. |
|
2018-08-15 |
Toni, Dragados |
AMC Box cabling |
No AMC Box installation because of holiday. Request in order to work on holiday, but Dragados did not want to work on holiday. |
|
2018-08-13 |
Toni, Dragados |
AMC Box cabling |
Because of rain no climbing works possible. |
|
2018-08-10 |
Martin, Casana |
IF plates & mirror installation |
7 mirrors were prepared on ground (Safety pin, CMOS camera, fix point). 9 mirrors were installed, 1 on the left, 2 in the very top and 6 on the right (view from front). |
|
2018-08-09 |
Martin, Satoshi, Casana |
IF plates & mirror installation |
3 missing Special IF plates were installed. 10 mirrors were prepared on ground (Safety pin, CMOS camera, fix point). 8 mirrors were installed, 3 in the very top and 5 on the left (view from front). |
|
Toni, Dragados |
AMC Box installation & cabling |
Dragados finished internal cabling of ~4 boxes (B,D,E,F). Toni brought up internal cables of 4 boxes (5,6,8,9). |
|
2018-08-08 |
Martin, Casana |
IF plates & mirror installation |
12 Special IF were installed. |
|
Satoshi, Dragados |
AMC Box installation & cabling |
Finished internal cables of 1 group (E). Started cabling of two boxes (B,D). |
|
2018-08-07 |
Martin, Casana |
IF plates & mirror installation |
1 Special IF was installed, more were not possible due to wind. Installation of missing tube holders finished. |
|
Christopher, Satoshi, Yusuke, Dragados |
AMC Box installation & cabling |
Started cabling from internal cables (box - mirrors). Finished actuator cables for 1 group (E). |
|
2018-08-06 |
Martin, Casana |
IF plates & mirror installation |
No installation of Special IF due to wind, installation of missing tube holders ongoing. |
|
Christopher, Dragados, Casana |
AMC Box installation & cabling |
Metal bars to fix AMC boxes lifted inside dish with cherry picker. Finished installation of all 16 boxes. |
|
2018-08-04 |
Christopher, Toni, Yusuke, Satoshi, Casana |
AMC Box installation & cabling |
All remaining AMC boxes lifted inside dish with cherry picker, secured in front of correct positions. |
|
2018-08-03 |
Martin |
IF plates & mirror installation |
7 missing tube spacers on 4 already installed IF plates installed. Rest will be done starting Monday by Casana. |
|
Christopher, Toni, Dragados |
AMC Box installation & cabling |
5 AMC boxes in lower half (C,7,F,B,D) installed. |
|
2018-08-02 |
Martin |
IF plates & mirror installation |
Tube spacers for Special IF plates and for already installed IF plates assembled. All 10 Special IF plates prepared and ready for installation. 5 Special IF plates for very top already prepared some months ago. |
|
Christopher, Martin, Toni, Yusuke, Satoshi, Dragados |
AMC Box installation & cabling |
Preparation of all 16 AMC boxes finished. Lowest AMC box (E) was installed and 6 boxes (C,7,A,F,B,D) lifted into the structure close to the correct positions inside the dish. |
|
2018-08-01 |
Martin, Casana |
IF plates & mirror installation |
Inspection of mirrors potentially damaged by falling CSS rope. One spot found, unknown if actual damage. Mirror to be exchanged. |
|
2018-07-31 |
Martin, Satoshi |
IF plates & mirror installation |
Almost all of the 10 Special IF plates prepared: level actuators, attach tube holder. Still missing tube connector plates (available Thu), attaching actuator caps, leveling fixed points. |
|