Commissioning Shift P3
Revision as of 11:00, 25 February 2019 by MartinWill (talk | contribs) (Created page with "* Commissioning Shift Period: 3 * Dates: 17.2.2019 - 3.3.2019 * Commissioning Shift Leader: Martin Will * Commissioning Shifters: ** Drive: Inocencio, Thierry (23/02-) ** Came...")
- Commissioning Shift Period: 3
- Dates: 17.2.2019 - 3.3.2019
- Commissioning Shift Leader: Martin Will
- Commissioning Shifters:
- Drive: Inocencio, Thierry (23/02-)
- Camera: Lea, Shunsuke, Seiya, Tomohiko, Oscar, Gustavo
- AMC / Mirrors: Satoshi, Tomohiro
Back to Commissioning Logbooks.
Commissioning Leader Diary
Daily List of Tests and Installations
Date | Category / System | Activities | Documents / Pictures |
---|---|---|---|
2019-02-17 Sunday |
Drive | ||
Camera | |||
AUX | |||
Other | Day off. Check of conditions at site. P1 CL Riccardo R. arrived on site, no overlap with previous CL (since there was none). | ||