Commissioning Shift P12
Contents
- 1 P12 (21.6.2019 - 8.7.2019)
- 2 Summaries and Results of Tests and Installations
- 3 Planned Actions
- 3.1 Sunday June 23rd (evening)
- 3.2 Monday June 24th
- 3.3 Tuesday June 25th
- 3.4 Wednesday June 26th
- 3.5 Thursday June 27th
- 3.6 Friday June 28th
- 3.7 Saturday June 29th
- 3.8 Sunday June 30th
- 3.9 Monday July 1st
- 3.10 Tuesday July 2nd
- 3.11 Wednesday July 3rd
- 3.12 Thursday July 4th
- 3.13 Friday July 5th
- 3.14 Saturday July 6th
- 3.15 Sunday July 7th
P12 (21.6.2019 - 8.7.2019)
- Commissioning Shift Period: 12
- Dates: 24.5.2019 - 10.6.2019
- Commissioning Shift Leader: Dirk Hoffmann
- Commissioning Shifters / Experts:
- Drive: Thierry Le Flour, Ino Monteiro (until 28.6.)
- Camera: Takayuki Saito (not on 27.6.), Shunsuke Saturai (until 26.6.), Yokiho Kobayashi, Mitsunari (from 27.6.)
- AMC / Mirrors: Koji Noda (until 21.6.)
- Former CSL: José Miguel Miranda (until 25.6.)
- Others: Thomas Schweizer (27.-28.6.)
- Shifter: Noah Biederbeck (from 1.7.)
Summaries and Results of Tests and Installations
E-log starting on June 23rd is here.
Planned Actions
Sunday June 23rd (evening)
Taking data for camera timing calibration, using CaliBox pulses.
Pictures of sunspots and more studies taken by José Miguel and Koji Noda. My contributions.
Monday June 24th
Camera timing calibration
EVB tests
Drive tests
Tuesday June 25th
Investigations on LIDAR events observed in run #591.
Camera timing calibration
EVB tests
Drive tests
Wednesday June 26th
Deploying new EVBv3 on *osaka*.
Drive: tracking tests continued
Thursday June 27th
Power cut from 9:00 to 14:00! Computers will run on diesel.
Install EVBv3.1 on *osaka*, then on *okinawa*. Reproduce yesterday's results on both.
Training for Drive operation by "expert shifters"
Friday June 28th
CAM meeting (9:00-11:00)
"CAM Container" visit with Thomas (Taka, Dirk)
EVBv3 consolidation (*okinawa*), training of Mitsunari (arrives today)
14:00 New CaCo version (2h)
16:00 EVB consolidation
Mirror checks
20:00 Light irradiation monitoring
21:00 Sky data taking
Saturday June 29th
Week-end
Sunday June 30th
EVB tests in the night (random, data correction)?
Monday July 1st
ITC / CamSrv installation cleanup postponed to Wednesday (CC work)
EVBv3 tests
CaCo repair
Tuesday July 2nd
EVBv3 debug (trying to go properly to READY)
Wednesday July 3rd
Intervention on CC floor
ELog-email connection
Arrange NICs in osaka for EVBv3 optimisation
Thursday July 4th
Intervention on CC floor
Friday July 5th
Bringing new CSL up to speed
Saturday July 6th
Handover/Overlap with new CSL
Sunday July 7th
Overlap with new CSL