Commissioning Shift P12

From my_wiki
Revision as of 08:28, 5 July 2019 by DirkHoffmann (talk | contribs) (Friday July 5th)
Jump to: navigation, search

P12 (21.6.2019 - 8.7.2019)

  • Commissioning Shift Period: 12
  • Dates: 24.5.2019 - 10.6.2019
  • Commissioning Shift Leader: Dirk Hoffmann
  • Commissioning Shifters / Experts:
    • Drive: Thierry Le Flour, Ino Monteiro (until 28.6.)
    • Camera: Takayuki Saito (not on 27.6.), Shunsuke Saturai (until 26.6.), Yokiho Kobayashi, Mitsunari (from 27.6.)
    • AMC / Mirrors: Koji Noda (until 21.6.)
    • Former CSL: José Miguel Miranda (until 25.6.)
    • Others: Thomas Schweizer (27.-28.6.)
  • Shifter: Noah Biederbeck (from 1.7.)

Summaries and Results of Tests and Installations

E-log starting on June 23rd is here.

Planned Actions

Sunday June 23rd (evening)

Taking data for camera timing calibration, using CaliBox pulses.

Pictures of sunspots and more studies taken by José Miguel and Koji Noda. My contributions.

Monday June 24th

Camera timing calibration

EVB tests

Drive tests

Tuesday June 25th

Investigations on LIDAR events observed in run #591.

Camera timing calibration

EVB tests

Drive tests

Wednesday June 26th

Deploying new EVBv3 on *osaka*.

Drive: tracking tests continued

Thursday June 27th

Power cut from 9:00 to 14:00! Computers will run on diesel.

Install EVBv3.1 on *osaka*, then on *okinawa*. Reproduce yesterday's results on both.

Training for Drive operation by "expert shifters"

Friday June 28th

CAM meeting (9:00-11:00)

"CAM Container" visit with Thomas (Taka, Dirk)

EVBv3 consolidation (*okinawa*), training of Mitsunari (arrives today)

14:00 New CaCo version (2h)

16:00 EVB consolidation

Mirror checks

20:00 Light irradiation monitoring

21:00 Sky data taking

Saturday June 29th

Week-end

Sunday June 30th

EVB tests in the night (random, data correction)?

Monday July 1st

ITC / CamSrv installation cleanup postponed to Wednesday (CC work)

EVBv3 tests

CaCo repair

Tuesday July 2nd

EVBv3 debug (trying to go properly to READY)

Night

Trigger rate scans and Pedestal datataking (Commissioning Plan "Camera diamonds 6, 8"). HV on, shutter off (at the end).

No telescope moves today, due to detached foam noodles on arch cables!

Wednesday July 3rd

Intervention on CC floor

Remote debug of EVBv3 GOTOREADY (with Julien), from MAGIC house [needs green light from Daniel]

If possible, check EVBv3 on okinawa.

ELog-email connection

Night

Pedestal runs (Commissioning Plan "Diamond 8")

Tracking + sky data (60')

Thursday July 4th

Intervention on CC floor

Arrange NICs in osaka for EVBv3 optimisation

Night

EVBv3 debug with Julien

Pedestal runs (Commissioning Plan "Diamond 8")

(No further tasks, tracking dark spot for NBS backgrounds.)

Friday July 5th

Agreed to start at 11:00, after last night shift.

  • Final EVBv3 rate scans (random) after installation from RPM
  • Trying okinawa again?
  • DRAGON-stuck investigations: use port copy / wireshark
  • OPC UA with EVBv3 (from RPM)
  • Operating EVB with user *lstoperator*
  • BP tests with Gustavo/Carlos? shifted to next week
    • test with TP and without HV where we perform the initialization, read the settings coarse and fine delay setting from the BP, using TP measure the up+down time, and repeat the cycle again, two or three times?


Bringing new CSL up to speed

Night

Pedestal runs (Commissioning Plan "Diamond 8")

Saturday July 6th

Contingency

Handover/Overlap with new CSL

Sunday July 7th

Overlap with new CSL