Commissioning Shift P12
Contents
- 1 P12 (21.6.2019 - 8.7.2019)
- 2 Summaries and Results of Tests and Installations
- 3 Regular datataking (done from Friday of 1st week on)
- 4 Planned Actions
- 4.1 Sunday June 23rd (evening)
- 4.2 Monday June 24th
- 4.3 Tuesday June 25th
- 4.4 Wednesday June 26th
- 4.5 Thursday June 27th
- 4.6 Friday June 28th
- 4.7 Saturday June 29th
- 4.8 Sunday June 30th
- 4.9 Monday July 1st
- 4.10 Tuesday July 2nd
- 4.11 Wednesday July 3rd
- 4.12 Thursday July 4th
- 4.13 Friday July 5th
- 4.14 Saturday July 6th
- 4.15 Sunday July 7th
P12 (21.6.2019 - 8.7.2019)
- Commissioning Shift Period: 12
- Dates: 24.5.2019 - 10.6.2019
- Commissioning Shift Leader: Dirk Hoffmann
- Commissioning Shifters / Experts:
- Drive: Thierry Le Flour, Ino Monteiro (until 28.6.)
- Camera: Takayuki Saito (not on 27.6.), Shunsuke Saturai (until 26.6.), Yokiho Kobayashi, Mitsunari (from 27.6.)
- AMC / Mirrors: Koji Noda (until 21.6.)
- Former CSL: José Miguel Miranda (until 25.6.)
- Others: Thomas Schweizer (27.-28.6.)
- Shifter: Noah Biederbeck (from 1.7.)
Summaries and Results of Tests and Installations
E-log starting on June 23rd is here.
Regular datataking (done from Friday of 1st week on)
Taken every night, if availability of staff (at least 1 shifter + 1 camera shifter + Commissioning Leader) and meteorological conditions (Watch humidity and temperature limits of camera!) allow.
Note all runs in eLog and RunCatalog!
- Prepare night data taking (last point), if applicable
- Unlock telescope
- Focus mirrors at sunset (not before!)
- HV off, shutter closed
- Pedestal 1kHz constant frequency (TIB-triggered): 100k events
- Pedestal 1kHz random (DRAGON-triggered): 100k events
- HV on (shutter still closed)
- Pedestal 1kHz constant frequency (TIB-triggered): 100k events
- Pedestal 1kHz random (DRAGON-triggered): 100k events
- Switch on calibration laser, if to be used later
- Park out telescope (earliest after sunset)
- Move to dark spot.
- RA=211.08°/Dec=+29.52° is a good candidate; you may have others.
- Open the shutter in park position (ZA limit 60°!), but then move to dark spot (to avoid passing cars' lights).
- Pedestal 1kHz constant frequency (TIB-triggered): 100k events
- Pedestal 1kHz random (DRAGON-triggered): 100k events
- Calibration pulses (L1-triggered) 1kHz constant frequency
- Pointing
- Select a target (ask experts, or chose a reasonably active source)
- Kill noisy pixels
- Taka data for max. 1 hours
Planned Actions
Sunday June 23rd (evening)
Taking data for camera timing calibration, using CaliBox pulses.
Pictures of sunspots and more studies taken by José Miguel and Koji Noda. My contributions.
Monday June 24th
Camera timing calibration
EVB tests
Drive tests
Tuesday June 25th
Investigations on LIDAR events observed in run #591.
Camera timing calibration
EVB tests
Drive tests
Wednesday June 26th
Deploying new EVBv3 on *osaka*.
Drive: tracking tests continued
Thursday June 27th
Power cut from 9:00 to 14:00! Computers will run on diesel.
Install EVBv3.1 on *osaka*, then on *okinawa*. Reproduce yesterday's results on both.
Training for Drive operation by "expert shifters"
Friday June 28th
CAM meeting (9:00-11:00)
"CAM Container" visit with Thomas (Taka, Dirk)
EVBv3 consolidation (*okinawa*), training of Mitsunari (arrives today)
14:00 New CaCo version (2h)
16:00 EVB consolidation
Mirror checks
20:00 Light irradiation monitoring
21:00 Sky data taking
Saturday June 29th
Week-end
Sunday June 30th
EVB tests in the night (random, data correction)?
Monday July 1st
ITC / CamSrv installation cleanup postponed to Wednesday (CC work)
EVBv3 tests
CaCo repair
Tuesday July 2nd
EVBv3 debug (trying to go properly to READY)
Night
Trigger rate scans and Pedestal datataking (Commissioning Plan "Camera diamonds 6, 8"). HV on, shutter off (at the end).
No telescope moves today, due to detached foam noodles on arch cables!
Wednesday July 3rd
Intervention on CC floor
Remote debug of EVBv3 GOTOREADY (with Julien), from MAGIC house [needs green light from Daniel]
If possible, check EVBv3 on okinawa.
ELog-email connection
Night
Pedestal runs (Commissioning Plan "Diamond 8")
Tracking + sky data (60')
Thursday July 4th
Intervention on CC floor
Arrange NICs in osaka for EVBv3 optimisation
Night
EVBv3 debug with Julien
Pedestal runs (Commissioning Plan "Diamond 8")
(No further tasks, tracking dark spot for NBS backgrounds.)
Friday July 5th
Agreed to start at 11:00, after last night shift.
- Install EVBv3 on osaka [DONE]
- Final EVBv3 rate scans (random) after installation from RPM [DONE]
- DRAGON-stuck investigations: use port copy / wireshark [DONE]
- OPC UA with EVBv3 (from RPM)
- Operating EVB with user lstoperator [DONE]
- Trying okinawa again [DONE]
BP tests with Gustavo/Carlos?shifted to next week- test with TP and without HV where we perform the initialization, read the settings coarse and fine delay setting from the BP, using TP measure the up+down time, and repeat the cycle again, two or three times?
Casana continues work in CC (floor of server compartment)
Bringing new CSL up to speed
Night
Pedestal runs (Commissioning Plan "Diamond 8")
Sky data
Saturday July 6th
Contingency
Handover/Overlap with new CSL
Sunday July 7th
Overlap with new CSL