Date |
Who did it? |
Action |
Comments |
Documents
|
2017-06-14 |
Garafia |
Town hall of Garafia issues license for mechanical installation |
|
|
2017-01-11 |
Dragados |
Foundation works finish |
|
|
2016-11-18 |
ICRR/IAC |
Requested license for mechanical installation |
|
|
2016-07-19 |
Dragados |
Foundation works start ("acta de replanteo") |
|
|
2016-07-25 |
Garafia |
Town hall of Garafia requests license for mechanical installation |
|
|
2016-06-15 |
IFAE |
Paid foundation license fee |
Total cost 31500 € |
|
2016-05-11 |
Garafia |
Town hall of Garafia issues second step of license for foundation |
|
|
2016-05-10 |
IAC |
Tender finishes. Company Dragados selected |
|
|
2015-12-11 |
IAC |
Tender for foundation published (in Spanish BOE) |
|
|
2015-11-10 |
Architect |
Requested second step of license for foundation |
Paid a fraction of estimated license tax |
|
2015-11-09 |
Architect's association |
La Palma architect's official association accepts final foundation drawings ("project") |
|
|
2015-10-22 |
Cabildo |
Cabildo issues first step of license for foundation |
|
|
2015-03-16 |
IFAE/Architect |
Request first step of license for foundation ("recalificación") |
|
|
2015-03-15 |
Architect (Estudio AT3) |
Foundation preliminary drawings ("pre-project"), including environmental study, finished |
|
|
2015-01-15 |
Icinco |
Company Icinco delivers geotechnical study |
|
|
2014-11-15 |
IFAE (Cortina) |
Company Icinco hired for geotechnical study |
Paid full cost 3600 € (incl. IGIC) |
|
2014-12-15 |
IFAE (Cortina) |
Contract between IFAE and architect signed |
Paid half of cost (12000 € net) |
|
2014-10-01 |
IFAE (Cortina) |
Started bidding to hire foundation architect |
|
|