Logbook Mirror-Tests-Mirca-NovDec2017
Revision as of 12:29, 25 November 2017 by Satoshifukami (talk | contribs) (→Enter comments in reverse time order)
Enter comments in reverse time order
Date | Who did it? | Action | Comments | Documents |
---|---|---|---|---|
2017-11-23 | Satoshi, Taku | Actuator Setup | finished 4 groups (16/16 in total) | |
2017-11-22 | Satoshi, Taku | Actuator Setup | finished 5 groups (12/16 in total) | |
2017-11-21 | Satoshi, Taku | Actuator Setup | finished 5 groups (7/16 in total) | |
2017-11-20 | Satoshi, Taku | Actuator Setup | prepared a big paper to write down actuator positions in the dish. started setups (radio frequency, group ID, packetization timeout and rotation speed & motor length of the actuators). finished 2 groups (2/16 in total) | |
2017-11-19 | Satoshi, Taku | Actuator Setup | 191 sets of actuators finally arrived! | |
2017-11-15 | Satoshi, Taku | IF plate assembly | We removed unnecessary plates from all of the 38 actuators here | |
2017-11-02 | Satoshi Fukami | Arrival in La Palma | Safetly arrived in La Palma. |