Logbook Camera-Assembly
Enter comments in reverse time order
Date | Who did it? | Action | Comments | Documents |
---|---|---|---|---|
2018-04-27 | Javier G., Carlos Díaz, Miguel Polo, Laia Cardiel, Otger Ballester, Sebastian Grinspun, Oscar Blanch, Merve Colak, Daniel Kerszberg | Camera arrived at IFAE from CIEMAT
Camera was unload and introduced in the shielded room Together with the camera, the chiller (as well as pipes) and the hydraulic system to open frontal door arrived to IFAE. Carlos Díaz and Miguel Polo open the back door of the camera. 3-Phase and 1-Phase power connected to the camera Ethernet RJ45 cable connected to main switch inside the camera long enough to be connected to a computer outside the shielded room (See Picture 4) which will be needed for ECC validation from May 1st to May 3rd. |
[https:https://docs.google.com/document/d/19-VtR1CCgBSi3tBuHC9_rrZ8CRMQoECY5PYHJguBokI drive] | |
2018-04-25 | Javi Gaweda, Noel | Space around the Shielded Room is prepared for the camera arrival;
Wall of the shielded room open to allow to enter the camera. |
drive | |
2018-04-24 | drive | |||
2018-04-23 | drive | |||
2018-04-20 | drive | |||
2018-04-19 | drive | |||
2018-04-18 | drive | |||
2018-04-17 | drive | |||
2018-04-16 | drive | |||
2018-04-13 | Camilla, Lea, Quim & Oscar |
Power connection mounted and tested. Communication with 10 modules checked. |
drive | |
2018-04-12 | Camilla, Lea, Quim & Oscar | Vertical bus bar arrived;
Problem with the plugs cable from the bus bar to the back plane; Joan and Alex are building new cable (cables have been plugged manually and fixed with tape by Lea&Quim); Mezzanines attached; 3-phase power supply wired, but not yet plugged; |
drive | |
2018-04-11 |
Camilla, Lea, Quim & Oscar || The set up for 10 modules is organized; Larger switch (to allow for 10 modules); 1 3-phase power supply (2 spares) but not yet wired; |
drive |