Logbook AMCBox
Revision as of 10:36, 8 August 2018 by Satoshifukami (talk | contribs) (→Enter comments in reverse time order)
Enter comments in reverse time order
Date | Who did it? | Action | Comments | Documents |
---|---|---|---|---|
2018-08-07 | Christopher, Satoshi, Yusuke, Dragados | AMC cabling | We started from internal cables (box - mirrors). We finished actuator cables for 1 group (E). | |
2018-08-06 | Christopher, Dragados, Casana | AMC box installation | We brought metal bars with a cherry picker and finished the installation of all the 16 boxes. | |
2018-08-04 | Christopher, Toni, Yusuke, Satoshi, Casana | AMC box installation | We brought up all the remained boxes in front of the correct positions with a cherry picker. | |
2018-08-03 | Martin | IF plates assembly | 7 missing tube spacers on 4 already installed IF plates installed. Rest will be done starting Monday by Casana. | |
2018-08-03 | Christopher, Toni, Dragados | IF plates assembly | We installed 5 AMC box of the lower half (C,7,F,B,D). | |
2018-08-02 | Christopher, Martin, Toni, Yusuke, Satoshi, Dragados | AMC box installation | Yusuke and Satoshi finished preparation of the 16 boxes. We installed one AMC box (E, at the lowest) and brought up 6 boxes (C,7,A,F,B,D) near the correct positions inside the dish. | |
2018-08-02 | Martin | IF plates assembly | Tube spacers for special special IF plates and for already installed IF plates assembled. All IF plates ready for installation on Monday. | |
2018-07-31 | Martin, Satoshi | IF plates assembly | We prepared almost all of the 10 special special IF plates (except attaching actuator caps, leveling fixed points and finishing tube spacers). |