Date |
Who did it? |
Action |
Comments |
Documents
|
2018-08-14 |
|
AMC Box installation & cabling |
|
|
2018-08-13 |
|
AMC Box installation & cabling |
|
|
2018-08-10 |
Martin, Casana |
IF plates & mirror installation |
7 mirrors were prepared on ground (Safety pin, CMOS camera, fix point). 9 mirrors were installed, 1 on the left, 2 in the very top and 6 on the right (view from front). |
|
|
AMC Box installation & cabling |
|
|
2018-08-09 |
Martin, Satoshi, Casana |
IF plates & mirror installation |
3 missing Special IF plates were installed. 10 mirrors were prepared on ground (Safety pin, CMOS camera, fix point). 8 mirrors were installed, 3 in the very top and 5 on the left (view from front). |
|
|
AMC Box installation & cabling |
|
|
2018-08-08 |
Martin, Casana |
IF plates & mirror installation |
12 Special IF were installed. |
|
Satoshi, Dragados |
AMC Box installation & cabling |
Finished internal cables of 1 group (E). Started cabling of two boxes (B,D). |
|
2018-08-07 |
Martin, Casana |
IF plates & mirror installation |
1 Special IF was installed, more were not possible due to wind. Installation of missing tube holders finished. |
|
Christopher, Satoshi, Yusuke, Dragados |
AMC Box installation & cabling |
Started cabling from internal cables (box - mirrors). Finished actuator cables for 1 group (E). |
|
2018-08-06 |
Martin, Casana |
IF plates & mirror installation |
No installation of Special IF due to wind, installation of missing tube holders ongoing. |
|
Christopher, Dragados, Casana |
AMC Box installation & cabling |
Metal bars to fix AMC boxes lifted inside dish with cherry picker. Finished installation of all 16 boxes. |
|
2018-08-04 |
Christopher, Toni, Yusuke, Satoshi, Casana |
AMC Box installation & cabling |
All remaining AMC boxes lifted inside dish with cherry picker, secured in front of correct positions. |
|
2018-08-03 |
Martin |
IF plates & mirror installation |
7 missing tube spacers on 4 already installed IF plates installed. Rest will be done starting Monday by Casana. |
|
Christopher, Toni, Dragados |
AMC Box installation & cabling |
5 AMC boxes in lower half (C,7,F,B,D) installed. |
|
2018-08-02 |
Martin |
IF plates & mirror installation |
Tube spacers for Special IF plates and for already installed IF plates assembled. All 10 Special IF plates prepared and ready for installation. 5 Special IF plates for very top already prepared some months ago. |
|
Christopher, Martin, Toni, Yusuke, Satoshi, Dragados |
AMC Box installation & cabling |
Preparation of all 16 AMC boxes finished. Lowest AMC box (E) was installed and 6 boxes (C,7,A,F,B,D) lifted into the structure close to the correct positions inside the dish. |
|
2018-08-01 |
Martin, Casana |
IF plates & mirror installation |
Inspection of mirrors potentially damaged by falling CSS rope. One spot found, unknown if actual damage. Mirror to be exchanged. |
|
2018-07-31 |
Martin, Satoshi |
IF plates & mirror installation |
Almost all of the 10 Special IF plates prepared: level actuators, attach tube holder. Still missing tube connector plates (available Thu), attaching actuator caps, leveling fixed points. |
|