246
|
Tue Apr 16 10:10:55 2019 |
Drive Team- Ino&Thierry | PLC Software and Configuration | | Elevation setup | |
1 degree has been added to the
Elevation accordingly to the last measurement
given by Olger
|
|
251
|
Thu Apr 18 21:21:25 2019 |
Drive Team- Ino&Thierry&Alessandro | Telescope Operations | Hardware | Elevation limit switch issue | |
The 2 swicthes are too far |
|
227
|
Fri Jan 25 14:12:28 2019 |
Drive Team | Telescope Operations | General | Drive Movement : PArkin and Parkout | | Many parkin operations done. To confirm
the different movements , a Parkin test with
a azimuth position 20 and Elevation 70. |
|
237
|
Wed Mar 6 10:54:33 2019 |
Drive Team- Ino&Thierry&Armand | Telescope Operations | General | DRIVE : High Speed tests | |
The FW issue is not solved . No
movement can be done
The FW is
going to be restarted ==> It takes several |
|
259
|
Tue Jul 2 21:25:07 2019 |
Dirk Hoffmann | Applications | Software | Current & Power Monitoring stuck ("Socomec display") | | The Current&Power Monitoring was not
updated and hidden by two emtpy modal dialogue
windows. |
|
263
|
Sat Jul 6 22:47:38 2019 |
Dirk Hoffmann | Telescope Operations | General | Car flash from road above+ | | When checking the telescope visually outside,
while it was in the "park-out"
position, a car happened to pass by from |
|
247
|
Tue Apr 16 14:34:22 2019 |
Drive Team- Ino | Telescope Operations | Hardware | Cabling the azimuth end switches | |
Cabling the azimuth end switches.
|
|
273
|
Sun Nov 24 19:33:56 2019 |
Mathieu David Armand | Telescope Operations | General | CDM images for bending model | | - CDM images at park out position.
Exposure 100ms.
OARL on. |
|
274
|
Mon Nov 25 22:53:22 2019 |
Mathieu David Armand | Telescope Operations | | CDM images 19/11/25 | | Mg=1.25
DenebDark 60x1s
RA-2
TestTracking 60x1s Displacement
from Deneb RA-2
Deneb 60x1s
DenebLed |
|
275
|
Tue Nov 26 21:37:03 2019 |
David Sanchez, Armand Fiasson, Mathieu De Bony | Telescope Operations | | CDM bending model image 26-11-2019 | | The aim was to observe several stars with
different magnitude and check the sensitivity
of the CDM. We wanted to use a semi-automatic |
|
276
|
Wed Nov 27 21:27:29 2019 |
Mathieu David Armand | Telescope Operations | | CDM & SG images with alternative target | | |
|
226
|
Fri Jan 25 12:39:52 2019 |
Drive Team | Problem Fixed | Hardware | Brakes issues fixed | | The brake of the elevation issue has been
fixed. Operations on drive can be resumed. |
|
223
|
Wed Jan 23 11:26:29 2019 |
Drive Team | PLC Software and Configuration | General | Azimuth tuning | |
To define precisely the correction
to apply to Azimuth positionning, a set of movements
have been done to calculte the correction |
|
279
|
Mon Feb 10 14:57:56 2020 |
Ino + Gael + Thierry | Other | Hardware | Azimuth Locking System | Fixed | Last week we put in sevice the new ALS
completly modified:
_ Main System with new reducer. |
14x |
238
|
Wed Mar 6 14:58:51 2019 |
Drive Team- Ino&Thierry&Armand | Telescope Operations | General | Access tower failure | | During a park-in action , the acces tower
did not close correctly. |
|
277
|
Sat Dec 7 19:16:01 2019 |
Daniel Mazin, Koji Noda | Hardware | Hardware | ALS East: problem and preliminary solution | | On Dec 6, Dario, Frederic and Yuji showed
to Koji Noda and Daniel Mazin how to operate
the new ALS. The idea was to do an unlock |
6x |
224
|
Wed Jan 23 15:10:34 2019 |
Drive Team | Telescope Operations | Hardware | | | Emergency stop applied because of a azimuth
value(encoder) not in the pre-defined range
+-0.015 |
|
225
|
Thu Jan 24 10:52:59 2019 |
Drive Team | Hardware | Issues | | | After issues during the parkin procedures
( 100% elveation torque ) :
a visual inpsection has |
|
Draft
|
Thu Jun 27 12:04:43 2019 |
Ino | Problem Fixed | General | | | During this 2 weeks we solve this problems:
_ Park In: Sometimes the final
locking position was too limit and the "In |
|
270
|
Thu Sep 12 16:41:53 2019 |
Drive Team- Ino&Thierry | PLC + Control Software debugging | | | | Tuesday September 110th :
Tests park-in and park-out
to manage the different type of failures
Tests |
|