Difference between revisions of "Commissioning Shift P1"
m (→Daily List of Tests and Installations) |
m |
||
(5 intermediate revisions by 2 users not shown) | |||
Line 3: | Line 3: | ||
* Commissioning Shift Leader: Riccardo Rando | * Commissioning Shift Leader: Riccardo Rando | ||
* Commissioning Shifters: | * Commissioning Shifters: | ||
− | ** Drive: Armand, Inocencio, Thierry (22/01-25/01), Alessandro (27/01-) | + | ** Drive: Armand, Inocencio, Thierry (22/01-25/01), Alessandro (27/01-), Juli, Rafael (31/01-) |
− | ** Camera: Elena (-), Mitsunari (21/01-), Taka (27/01-) | + | ** Camera: Elena (-), Mitsunari (21/01-30/01), Taka (27/01-) |
− | ** Aux: Koji (28/01-) | + | ** Aux: Koji (28/01-), Taku (28/01-) |
Back to [[Logbook_Commissioning|Commissioning Logbooks]]. | Back to [[Logbook_Commissioning|Commissioning Logbooks]]. | ||
Line 35: | Line 35: | ||
| 2019-01-21 || style="background: #add8e6;" | Drive || || | | 2019-01-21 || style="background: #add8e6;" | Drive || || | ||
|- | |- | ||
− | | Monday || style="background: #ade6bb;" | Camera || Some tests with | + | | Monday || style="background: #ade6bb;" | Camera || Some tests with L0 noise scans || |
|- | |- | ||
| || style="background: #e6e6ad;" | AUX || || | | || style="background: #e6e6ad;" | AUX || || | ||
Line 172: | Line 172: | ||
| || style="background: #e6e6ad;" | AUX || || | | || style="background: #e6e6ad;" | AUX || || | ||
|- | |- | ||
− | | || style="background: #ffcccb;" | Other || | + | | || style="background: #ffcccb;" | Other || Carlos D. arriving at 1345 at airport, Riccardo going to pick him up. || |
|- | |- |
Latest revision as of 10:05, 1 February 2019
- Commissioning Shift Period: 1
- Dates: 19.1.2019 - 4.2.2019
- Commissioning Shift Leader: Riccardo Rando
- Commissioning Shifters:
- Drive: Armand, Inocencio, Thierry (22/01-25/01), Alessandro (27/01-), Juli, Rafael (31/01-)
- Camera: Elena (-), Mitsunari (21/01-30/01), Taka (27/01-)
- Aux: Koji (28/01-), Taku (28/01-)
Back to Commissioning Logbooks.
Commissioning Leader Diary[edit]
Daily List of Tests and Installations[edit]
Date | Category / System | Activities | Documents / Pictures |
---|---|---|---|
2019-01-20 | Drive | ||
Sunday | Camera | ||
AUX | |||
Other | Day off. Check of conditions at site. P1 CL Riccardo R. arrived on site, no overlap with previous CL (since there was none). | ||
2019-01-21 | Drive | ||
Monday | Camera | Some tests with L0 noise scans | |
AUX | |||
Other | |||
2019-01-22 | Drive | Tests mission "Park In/Park Out" with all software chain (bug in December). Tests mission "Park In/Park Out" with cancel and restart at various intermediate position. Measurement of the elevation motor torque vs clamping vs arch cable tension | |
Tuesday | Camera | ||
AUX | |||
Other | |||
2019-01-23 | Drive | Test Go To Position Mission. Tests mission "Park In/Park Out" after AZ motions sequence. Setup for FACT scan: end of shift (18:30) align dish for maximum occultation, come back ~20:00 for park. Could not park due to anomalous torque on elevation, will park in the morning, azimuth is locked. | |
Wednesday | Camera | Review the procedure to apply HV to the PMTs during day time. If the review goes ok we will apply HV during night time. Rate scans to check the trigger mezzanines behaviour. | |
AUX | |||
Other | 10:00-11:00 - IT management switch exchange, no effect foreseen. | ||
2019-01-24 | Drive | Tests mission "Park In/Park Out" after AZ motions sequence. Verification of motor position vs shaft encoder position and tuning. Change: Manual park. Inspect elevation motor and brakes. | |
Thursday | Camera | Rate scans to check the trigger mezzanines behaviour. Tests of trigger calibrations. Check on supplying HV with the shutter open after 20:00. | |
AUX | |||
Other | Schedule will be affected by anomalous condition of elevation stage. | ||
2019-01-25 | Drive | Fix breaking system. | |
Friday | Camera | ||
AUX | |||
Other | Yusuke ~9:30 on site to install the UPS in the Comm. container | ||
2019-01-26 | Drive | Some tests until afternoon. | |
Saturday | Camera | ||
AUX | |||
Other | Day off | ||
2019-01-27 | Drive | Some tests from afternoon. | |
Sunday | Camera | ||
AUX | |||
Other | Day off | ||
2019-01-28 | Drive | Test of tracking Mission. | |
Monday | Camera | DAQ speed test with the fixed Nexus switch. | |
AUX | |||
Other | Ayumar: electrical works in op. room (cable from UPS, emergency lights). | ||
2019-01-29 | Drive | Test of tracking Mission | |
Tuesday | Camera | Replace NICs in the camera server Osaka to see if “interface-down problem” is fixed. DAQ speed test with new NICs. Will require access to camera back | |
AUX | |||
Other | Replace UPS in commissioning container with the correct one. | ||
2019-01-30 | Drive | ||
Wednesday | Camera | DAQ test with the current setup. If everything is good, NICs of Osaka will be replaced. Tests CaCo and trigger calibrations in CaCo | |
AUX | Tests IFAE and Koji (Flywheel discharge). Tests IFAE (vibration Measurement) | ||
Other | 10:30 - David Bristow & Paolo Calisse at the LST site. Daniel leaves in the afternoon. | ||
2019-01-31 | Drive | Calibration of the Elevation Zenith and verification at different position | |
Thursday | Camera | Install EVBV3 in Okinawa. Check Okinawa/Osaka parallel DAQ system. Tests CaCo and trigger calibrations in CaCo. L0 and L1 ratescans | |
AUX | Cabling of AMC Switch and Main cabinet Indicator Light | ||
Other | Put the sun mask on telescope. | ||
2019-02-01 | Drive | ||
Friday | Camera | Tests CaCo and trigger calibrations in CaCo. L0 and L1 ratescans | |
AUX | |||
Other | Carlos D. arriving at 1345 at airport, Riccardo going to pick him up. | ||
2019-02-02 | Drive | ||
Saturday | Camera | ||
AUX | |||
Other | Day off. Carlos D. on site for handshake | ||
2019-02-03 | Drive | ||
Sunday | Camera | ||
AUX | |||
Other | Day off. Carlos D. on site for handshake. Riccardo R. leaves around 17:00 |
| |