Commissioning Shift P1

From my_wiki
Jump to: navigation, search
  • Commissioning Shift Period: 1
  • Dates: 19.1.2019 - 4.2.2019
  • Commissioning Shift Leader: Riccardo Rando
  • Commissioning Shifters:
    • Drive: Armand, Inocencio, Thierry (22/01-25/01), Alessandro (27/01-), Juli, Rafael (31/01-)
    • Camera: Elena (-), Mitsunari (21/01-30/01), Taka (27/01-)
    • Aux: Koji (28/01-), Taku (28/01-)

Back to Commissioning Logbooks.

Commissioning Leader Diary[edit]

Commissioning_Leader_Diary_P1

Daily List of Tests and Installations[edit]

Date Category / System Activities Documents / Pictures
2019-01-20 Drive
Sunday Camera
AUX
Other Day off. Check of conditions at site. P1 CL Riccardo R. arrived on site, no overlap with previous CL (since there was none).
2019-01-21 Drive
Monday Camera Some tests with L0 noise scans
AUX
Other
2019-01-22 Drive Tests mission "Park In/Park Out" with all software chain (bug in December). Tests mission "Park In/Park Out" with cancel and restart at various intermediate position. Measurement of the elevation motor torque vs clamping vs arch cable tension
Tuesday Camera
AUX
Other
2019-01-23 Drive Test Go To Position Mission. Tests mission "Park In/Park Out" after AZ motions sequence. Setup for FACT scan: end of shift (18:30) align dish for maximum occultation, come back ~20:00 for park. Could not park due to anomalous torque on elevation, will park in the morning, azimuth is locked.
Wednesday Camera Review the procedure to apply HV to the PMTs during day time. If the review goes ok we will apply HV during night time. Rate scans to check the trigger mezzanines behaviour.
AUX
Other 10:00-11:00 - IT management switch exchange, no effect foreseen.
2019-01-24 Drive Tests mission "Park In/Park Out" after AZ motions sequence. Verification of motor position vs shaft encoder position and tuning. Change: Manual park. Inspect elevation motor and brakes.
Thursday Camera Rate scans to check the trigger mezzanines behaviour. Tests of trigger calibrations. Check on supplying HV with the shutter open after 20:00.
AUX
Other Schedule will be affected by anomalous condition of elevation stage.
2019-01-25 Drive Fix breaking system.
Friday Camera
AUX
Other Yusuke ~9:30 on site to install the UPS in the Comm. container
2019-01-26 Drive Some tests until afternoon.
Saturday Camera
AUX
Other Day off
2019-01-27 Drive Some tests from afternoon.
Sunday Camera
AUX
Other Day off
2019-01-28 Drive Test of tracking Mission.
Monday Camera DAQ speed test with the fixed Nexus switch.
AUX
Other Ayumar: electrical works in op. room (cable from UPS, emergency lights).
2019-01-29 Drive Test of tracking Mission
Tuesday Camera Replace NICs in the camera server Osaka to see if “interface-down problem” is fixed. DAQ speed test with new NICs. Will require access to camera back
AUX
Other Replace UPS in commissioning container with the correct one.
2019-01-30 Drive
Wednesday Camera DAQ test with the current setup. If everything is good, NICs of Osaka will be replaced. Tests CaCo and trigger calibrations in CaCo
AUX Tests IFAE and Koji (Flywheel discharge). Tests IFAE (vibration Measurement)
Other 10:30 - David Bristow & Paolo Calisse at the LST site. Daniel leaves in the afternoon.
2019-01-31 Drive Calibration of the Elevation Zenith and verification at different position
Thursday Camera Install EVBV3 in Okinawa. Check Okinawa/Osaka parallel DAQ system. Tests CaCo and trigger calibrations in CaCo. L0 and L1 ratescans
AUX Cabling of AMC Switch and Main cabinet Indicator Light
Other Put the sun mask on telescope.
2019-02-01 Drive
Friday Camera Tests CaCo and trigger calibrations in CaCo. L0 and L1 ratescans
AUX
Other Carlos D. arriving at 1345 at airport, Riccardo going to pick him up.
2019-02-02 Drive
Saturday Camera
AUX
Other Day off. Carlos D. on site for handshake
2019-02-03 Drive
Sunday Camera
AUX
Other Day off. Carlos D. on site for handshake. Riccardo R. leaves around 17:00