Difference between revisions of "Commissioning Shift P1"
MartinWill (talk | contribs) |
|||
Line 3: | Line 3: | ||
* Commissioning Shift Leader: Riccardo Rando | * Commissioning Shift Leader: Riccardo Rando | ||
* Commissioning Shifters: | * Commissioning Shifters: | ||
− | ** Drive: | + | ** Drive: Armand, Inocencio, Thierry (22/01-25/01), Alessandro (27/01-) |
− | ** | + | ** Camera: Elena (-), Mitsunari (21/01-), Taka (27/01-) |
− | ** | + | ** Aux: Koji (28/01-) |
Back to [[Logbook_Commissioning|Commissioning Logbooks]]. | Back to [[Logbook_Commissioning|Commissioning Logbooks]]. |
Revision as of 14:35, 29 January 2019
- Commissioning Shift Period: 1
- Dates: 19.1.2019 - 4.2.2019
- Commissioning Shift Leader: Riccardo Rando
- Commissioning Shifters:
- Drive: Armand, Inocencio, Thierry (22/01-25/01), Alessandro (27/01-)
- Camera: Elena (-), Mitsunari (21/01-), Taka (27/01-)
- Aux: Koji (28/01-)
Back to Commissioning Logbooks.
Commissioning Leader Diary
Daily List of Tests and Installations
Date | Category / System | Action | Comments | Documents / Pictures |
---|---|---|---|---|
2019-01-20 | CL | Check of conditions at site | P1 CL R. Rando arrived on site, no overlap with previous CL (since there was none). | |
2019-01-21 | CL | Day off | No activities on site. | |
2019-01-22 | Drive | |||
2019-01-22 | Camera | |||
2019-01-22 | AMC | |||