Difference between revisions of "Commissioning Shift P1"
(→Daily List of Tests and Installations) |
(→Daily List of Tests and Installations) |
||
Line 55: | Line 55: | ||
|| | || | ||
|- | |- | ||
− | | Wednesday || style="background: #ade6bb;" | Camera || Review the procedure to apply HV to the PMTs during day time. If the review goes ok we will apply it during night time. | + | | Wednesday || style="background: #ade6bb;" | Camera || Review the procedure to apply HV to the PMTs during day time. If the review goes ok we will apply it during night time. Rate scans to check the trigger mezzanines behaviour. || |
− | Rate scans to check the trigger mezzanines behaviour. | ||
|- | |- | ||
| || style="background: #e6e6ad;" | AUX || || | | || style="background: #e6e6ad;" | AUX || || | ||
Line 90: | Line 89: | ||
|- | |- | ||
− | | 2019-01-26 || style="background: #add8e6;" | Drive || | + | | 2019-01-26 || style="background: #add8e6;" | Drive || Some tests until afternoon. || |
|- | |- | ||
| Saturday || style="background: #ade6bb;" | Camera || || | | Saturday || style="background: #ade6bb;" | Camera || || | ||
Line 96: | Line 95: | ||
| || style="background: #e6e6ad;" | AUX || || | | || style="background: #e6e6ad;" | AUX || || | ||
|- | |- | ||
− | | || style="background: #ffcccb;" | Other || | + | | || style="background: #ffcccb;" | Other || Day off || |
|- | |- | ||
Line 102: | Line 101: | ||
|- | |- | ||
− | | 2019-01-27 || style="background: #add8e6;" | Drive || | + | | 2019-01-27 || style="background: #add8e6;" | Drive || Some tests from afternoon. || |
|- | |- | ||
| Sunday || style="background: #ade6bb;" | Camera || || | | Sunday || style="background: #ade6bb;" | Camera || || | ||
Line 108: | Line 107: | ||
| || style="background: #e6e6ad;" | AUX || || | | || style="background: #e6e6ad;" | AUX || || | ||
|- | |- | ||
− | | || style="background: #ffcccb;" | Other || | + | | || style="background: #ffcccb;" | Other || Day off || |
|- | |- |
Revision as of 15:30, 29 January 2019
- Commissioning Shift Period: 1
- Dates: 19.1.2019 - 4.2.2019
- Commissioning Shift Leader: Riccardo Rando
- Commissioning Shifters:
- Drive: Armand, Inocencio, Thierry (22/01-25/01), Alessandro (27/01-)
- Camera: Elena (-), Mitsunari (21/01-), Taka (27/01-)
- Aux: Koji (28/01-)
Back to Commissioning Logbooks.
Commissioning Leader Diary
Daily List of Tests and Installations
Date | Category / System | Activities | Documents / Pictures |
---|---|---|---|
2019-01-20 | Other | Check of conditions at site. P1 CL R. Rando arrived on site, no overlap with previous CL (since there was none). | |
Sunday | |||
2019-01-21 | Drive | ||
Monday | Camera | Some tests with FSM state | |
AUX | |||
Other | |||
2019-01-22 | Drive | Tests mission "Park In/Park Out" with all software chain (bug in December). Tests mission "Park In/Park Out" with cancel and restart at various intermediate position. Measurement of the elevation motor torque vs clamping vs arch cable tension | |
Tuesday | Camera | ||
AUX | |||
Other | |||
2019-01-23 | Drive | Test Go To Position Mission. Tests mission "Park In/Park Out" after AZ motions sequence. Setup for FACT scan: end of shift (18:30) align dish for maximum occultation, come back ~20:00 for park. Could not park due to anomalous torque on elevation, will park in the morning, azimuth is locked. | |
Wednesday | Camera | Review the procedure to apply HV to the PMTs during day time. If the review goes ok we will apply it during night time. Rate scans to check the trigger mezzanines behaviour. | |
AUX | |||
Other | 10:00-11:00 - IT management switch exchange, no effect foreseen. | ||
2019-01-24 | Drive | Tests mission "Park In/Park Out" after AZ motions sequence. Verification of motor position vs shaft encoder position and tuning. Change: Manual park. Inspect elevation motor and brakes. | |
Thursday | Camera | Rate scans to check the trigger mezzanines behaviour. Tests of trigger calibrations. Check on supplying HV with the shutter open after 20:00. | |
AUX | |||
Other | Schedule will be affected by anomalous condition of elevation stage. | ||
2019-01-25 | Drive | Fix breaking system. | |
Friday | Camera | ||
AUX | |||
Other | Yusuke ~9:30 on site to install the UPS in the Comm. container | ||
2019-01-26 | Drive | Some tests until afternoon. | |
Saturday | Camera | ||
AUX | |||
Other | Day off | ||
2019-01-27 | Drive | Some tests from afternoon. | |
Sunday | Camera | ||
AUX | |||
Other | Day off | ||