Difference between revisions of "Commissioning Shift P1"
m (→Daily List of Tests and Installations) |
m |
||
Line 25: | Line 25: | ||
|- | |- | ||
− | | 2019-01-21 || style="background: # | + | | 2019-01-21 || style="background: #add8e6;" | Drive || || || |
|- | |- | ||
− | | Monday || style="background: #ade6bb;" | Camera || | + | | Monday || style="background: #ade6bb;" | Camera || Some tests with FSM state || || |
|- | |- | ||
| || style="background: #e6e6ad;" | AUX || || || | | || style="background: #e6e6ad;" | AUX || || || | ||
Line 37: | Line 37: | ||
|- | |- | ||
− | | 2019-01-22 || style="background: #add8e6;" | Drive || || || | + | | 2019-01-22 || style="background: #add8e6;" | Drive || Tests mission "Park In/Park" Out with all software chain. (Bug in December). Tests mission "Park In/Park Out" with cancel and restart at various intermediate position. Measurement of the elevation motor torque vs clamping vs arch cable tension |
+ | || || | ||
|- | |- | ||
| Tuesday || style="background: #ade6bb;" | Camera || || || | | Tuesday || style="background: #ade6bb;" | Camera || || || | ||
Line 43: | Line 44: | ||
| || style="background: #e6e6ad;" | AUX || || || | | || style="background: #e6e6ad;" | AUX || || || | ||
|- | |- | ||
− | | || style="background: #ffcccb;" | Other || || | + | | || style="background: #ffcccb;" | Other || || Road condition critical || |
|- | |- |
Revision as of 14:50, 29 January 2019
- Commissioning Shift Period: 1
- Dates: 19.1.2019 - 4.2.2019
- Commissioning Shift Leader: Riccardo Rando
- Commissioning Shifters:
- Drive: Armand, Inocencio, Thierry (22/01-25/01), Alessandro (27/01-)
- Camera: Elena (-), Mitsunari (21/01-), Taka (27/01-)
- Aux: Koji (28/01-)
Back to Commissioning Logbooks.
Commissioning Leader Diary
Daily List of Tests and Installations
Date | Category / System | Action | Comments | Documents / Pictures |
---|---|---|---|---|
2019-01-20 | Other | Check of conditions at site | P1 CL R. Rando arrived on site, no overlap with previous CL (since there was none). | |
2019-01-21 | Drive | |||
Monday | Camera | Some tests with FSM state | ||
AUX | ||||
Other | ||||
2019-01-22 | Drive | Tests mission "Park In/Park" Out with all software chain. (Bug in December). Tests mission "Park In/Park Out" with cancel and restart at various intermediate position. Measurement of the elevation motor torque vs clamping vs arch cable tension | ||
Tuesday | Camera | |||
AUX | ||||
Other | Road condition critical | |||
2019-01-23 | Drive | |||
Wednesday | Camera | |||
AUX | ||||
Other | ||||
2019-01-24 | Drive | |||
Thursday | Camera | |||
AUX | ||||
Other | ||||
2019-01-25 | Drive | |||
Friday | Camera | |||
AUX | ||||
Other | ||||
2019-01-26 | Drive | |||
Saturday | Camera | |||
AUX | ||||
Other | ||||
2019-01-27 | Drive | |||
Sunday | Camera | |||
AUX | ||||
Other | ||||