Commissioning Shift P1

From my_wiki
Revision as of 15:30, 29 January 2019 by Ricrando (talk | contribs) (Daily List of Tests and Installations)
Jump to: navigation, search
  • Commissioning Shift Period: 1
  • Dates: 19.1.2019 - 4.2.2019
  • Commissioning Shift Leader: Riccardo Rando
  • Commissioning Shifters:
    • Drive: Armand, Inocencio, Thierry (22/01-25/01), Alessandro (27/01-)
    • Camera: Elena (-), Mitsunari (21/01-), Taka (27/01-)
    • Aux: Koji (28/01-)

Back to Commissioning Logbooks.

Commissioning Leader Diary

Commissioning_Leader_Diary_P1

Daily List of Tests and Installations

Date Category / System Activities Documents / Pictures
2019-01-20 Other Check of conditions at site. P1 CL R. Rando arrived on site, no overlap with previous CL (since there was none).
Sunday
2019-01-21 Drive
Monday Camera Some tests with FSM state
AUX
Other
2019-01-22 Drive Tests mission "Park In/Park Out" with all software chain (bug in December). Tests mission "Park In/Park Out" with cancel and restart at various intermediate position. Measurement of the elevation motor torque vs clamping vs arch cable tension
Tuesday Camera
AUX
Other
2019-01-23 Drive Test Go To Position Mission. Tests mission "Park In/Park Out" after AZ motions sequence. Setup for FACT scan: end of shift (18:30) align dish for maximum occultation, come back ~20:00 for park. Could not park due to anomalous torque on elevation, will park in the morning, azimuth is locked.
Wednesday Camera Review the procedure to apply HV to the PMTs during day time. If the review goes ok we will apply it during night time. Rate scans to check the trigger mezzanines behaviour.
AUX
Other 10:00-11:00 - IT management switch exchange, no effect foreseen.
2019-01-24 Drive Tests mission "Park In/Park Out" after AZ motions sequence. Verification of motor position vs shaft encoder position and tuning. Change: Manual park. Inspect elevation motor and brakes.
Thursday Camera Rate scans to check the trigger mezzanines behaviour. Tests of trigger calibrations. Check on supplying HV with the shutter open after 20:00.
AUX
Other Schedule will be affected by anomalous condition of elevation stage.
2019-01-25 Drive Fix breaking system.
Friday Camera
AUX
Other Yusuke ~9:30 on site to install the UPS in the Comm. container
2019-01-26 Drive Some tests until afternoon.
Saturday Camera
AUX
Other Day off
2019-01-27 Drive Some tests from afternoon.
Sunday Camera
AUX
Other Day off