Commissioning Shift Information
Instructions and useful links for the LST Commissioning Leaders.
Emergency phone numbers | Public Emergency | (0) 112 | |- | Residencia Reception (day time) | (0) +34 922 405 500 (internal: 2500) | |- | Residencia Night Residencia Porter (night time)| (0) +34 609 554 576 | |- | Commissioning Leader: (0) +34 676 649 025 | |- | Telescope Manager (Patricia Márquez) | (0) +34 620 413 156 |
LST1 Commissioning Leaders
Overall Commissioning Plans 2019
- CW 12: Camera tests, mainly calibration. No optics tests planned, no drive tests planned. MPI team will come to make improvements in the mechanics
- CW 13: LAPP team is back, drive tests. Dirk and Julien: DAQ tests. Still unclear if the mirrors will be uncovered or not, depends how the next week goes.
Toni Dettlaff will do some optics work inside the dish, also some work in the commissioning container