Entry  Wed Mar 6 14:58:51 2019, Drive Team- Ino&Thierry&Armand, Telescope Operations, General, Access tower failure,  
During a park-in action , the acces tower did not close correctly.
Entry  Wed Mar 6 15:33:14 2019, Drive Team- Ino&Thierry&Armand, Telescope Operations, General, Test High Speed Drive,  

Test at 60% maximal speed from -90 to 0

 Check of the FW discharge : No error (FW 2 : 95% FW1 : 100%)


Test
at 60% maximal speed from -90 to 270

Check of the FW discharge ==> Error (FW 2 : 90 % FW1 : 100%)
Drive stops at 250
degree.
Power consumption = 60kw


 
Entry  Wed Mar 6 16:30:56 2019, Drive Team- Ino&Thierry&Armand, PLC + Control Software debugging, Software, Tracking mode debug,  

Debugging of the MOS plugin corresponding to the tracking 
Entry  Fri Mar 8 09:20:29 2019, Drive Team- Ino&Thierry&Armand, Telescope Operations, General, High speed drive tests,  

On Thrusday :

new movements at 45% from -90 to 270 have been done.
No possible movement at 60% because the FW and UPS
issues are not solved yet

Ino will back on site when HITACHI team will be on site for FW maintenance

Tests at 60% will
be done to validate (or not) the correction applied by Hitachi team.






Entry  Fri Mar 8 09:25:22 2019, Drive Team- Ino&Thierry&Armand, PLC + Control Software debugging, Software, Tracking debug and setup,  

Tracking procedure has been debugged from the GUI-MOS (OPCUA Server with tracking plugin)-PLC
Still some improvments to apply
but globally the procedure is running well.
Entry  Mon Apr 1 07:36:04 2019, Drive Team- Ino&Thierry&Armand, Telescope Operations, General, Tracking debug and setup,  

Regulation of the motors (PID) for slow and fast tracking and motor oscillations.
Implementation and Debugging of the Semi-Expert
control software for the drive.

GUIs + MOS plugin (OPCUA Server)


 Results are quite encouraging in good wheather
condiftions.

additionnal tests in different (wind) conditions are envisaged to validate completly the process


Entry  Mon Apr 1 07:43:23 2019, Drive Team- Ino&Thierry&Armand, Problem Fixed, Hardware, LST Parking control,  

On Wenesday morning (27/03/19) :

With Holger and Robert (MPI) , many telescope "park in/park out" operations have been
performed in order to refine the positionning in the acces tower and at the elevation locking bolt
Holger and Robert applied many mechanical modifications on the acces tower to make the telescope park operations very smooth
Entry  Wed Apr 17 21:26:13 2019, Drive Team- Ino&Thierry&Alessandro, Satoshi, Telescope Operations, General, Tracking for mirrors alignment,  

Tracking at position :

RA = 101.288541 RA Offset = -0.6
DEC = -16.71343 DEC Offset = 0.7


Entry  Thu Apr 18 21:07:20 2019, Drive Team- Ino&Thierry&Alessandro, Telescope Operations, , TESTS Parkout Parkin for fixing the bolt issue,  

Different ParkOut and Parkin done with different values for testing the torque limitation. 

By decreasing the torque and the
position , the parkin failed because we are not in the CSS locking sensor (in locking position)
By setting back the original values, th
parkin is ok but the bolt cannot be properly inserted.


Entry  Thu Apr 18 21:21:25 2019, Drive Team- Ino&Thierry&Alessandro, Telescope Operations, Hardware, Elevation limit switch issue,  ElevationEndSwicth.png


The 2 swicthes are too far from the target at 56.48 elevation.  The sensor have been tuned in parkin position and the distance was
correct (2mm) and at 56.48 is about 10mm. (impossible to tune correctly the sensor and the atrger has to be tuned)
Entry  Mon Sep 16 08:59:41 2019, Drive Team- Ino&Thierry + Ievgen + Vitalii + Jean-Luc, PLC + Control Software debugging, , Test TCU<->Drive,  
Thierry&Ino on site

Ievgen, Vitalli and Jean-Luc remotely.

TCU tests to perform the parkin-in and park-out procedure from the Drive.
Entry  Tue Feb 26 20:45:41 2019, Drive Team- Ino&Thierry, Telescope Operations, General, Tracking debug,  
Start of the tracking debug ==> PLC and MOS 
Entry  Tue Feb 26 20:47:15 2019, Drive Team- Ino&Thierry, Telescope Operations, General, Polaris point for mirrors aligment,  
Pointing to polaris ==>

Azimuth = 0.808

Elevation = 59.941 + 1 degree (correction)
Entry  Wed Feb 27 20:33:17 2019, Drive Team- Ino&Thierry, Telescope Operations, General, Polaris point for mirrors aligment,  
Same operations as yesterday ==> pointing to Polaris with the same coordinates
Entry  Thu Feb 28 19:56:55 2019, Drive Team- Ino&Thierry, PLC Software and Configuration, , Tracking debug and setup,  
Debugging of the tracking sequence :


PLC sequence : trajectory tracking data correctly managed
PLC tuning : regulation OK ==> need to refine.
Tracking
algorithm :

Changes in Drive.ccp to allow azimuth negative values.
Tracking duration : even by changing the duration of he tracking
Entry  Thu Feb 28 20:01:44 2019, Drive Team- Ino&Thierry, Telescope Operations, General, Polaris point for mirrors aligment,  
Same operations as yesterday ==> Polaris position
Entry  Tue Mar 5 14:42:22 2019, Drive Team- Ino&Thierry, Telescope Operations, General, High speed drive tests,  
. Fisrt day of the high speed drive tests with IFAE team.


Tests for tuning and generating motor plots at 10% (0.0234 Rad/s) of the maximal speed (GRB alert speed)
Tuning of the
emergency stop from 0.05 Rad/s2 up to 0.2 Rad/s2
6 movements at 25% speed. (from -90 to 270)
repositionnning to -90 at 40% 
movements
Entry  Tue Apr 16 10:10:55 2019, Drive Team- Ino&Thierry, PLC Software and Configuration, , Elevation setup,  

1 degree has been added to the Elevation accordingly to the last measurement given by Olger
Entry  Thu Sep 12 16:41:53 2019, Drive Team- Ino&Thierry, PLC + Control Software debugging, , ,  
Tuesday September 110th :


Tests park-in and park-out to manage the different type of failures 
Tests failure during park-in phase with a telescope
in a position different from the park-out position
Tests (from the Drive semi-expert GUI) to send the telecope to the parking area from any
Entry  Tue Apr 16 14:34:22 2019, Drive Team- Ino, Telescope Operations, Hardware, Cabling the azimuth end switches,  

Cabling the azimuth end switches.