Entry  Wed Mar 6 14:58:51 2019, Drive Team- Ino&Thierry&Armand, Telescope Operations, General, Access tower failure,  
Entry  Wed Mar 6 15:33:14 2019, Drive Team- Ino&Thierry&Armand, Telescope Operations, General, Test High Speed Drive,  
Entry  Wed Mar 6 16:30:56 2019, Drive Team- Ino&Thierry&Armand, PLC + Control Software debugging, Software, Tracking mode debug,  
Entry  Fri Mar 8 09:20:29 2019, Drive Team- Ino&Thierry&Armand, Telescope Operations, General, High speed drive tests,  
Entry  Fri Mar 8 09:25:22 2019, Drive Team- Ino&Thierry&Armand, PLC + Control Software debugging, Software, Tracking debug and setup,  
Entry  Mon Apr 1 07:36:04 2019, Drive Team- Ino&Thierry&Armand, Telescope Operations, General, Tracking debug and setup,  
Entry  Mon Apr 1 07:43:23 2019, Drive Team- Ino&Thierry&Armand, Problem Fixed, Hardware, LST Parking control,  
Entry  Wed Apr 17 21:26:13 2019, Drive Team- Ino&Thierry&Alessandro, Satoshi, Telescope Operations, General, Tracking for mirrors alignment,  
Entry  Thu Apr 18 21:07:20 2019, Drive Team- Ino&Thierry&Alessandro, Telescope Operations, , TESTS Parkout Parkin for fixing the bolt issue,  
Entry  Thu Apr 18 21:21:25 2019, Drive Team- Ino&Thierry&Alessandro, Telescope Operations, Hardware, Elevation limit switch issue,  ElevationEndSwicth.png
Entry  Mon Sep 16 08:59:41 2019, Drive Team- Ino&Thierry + Ievgen + Vitalii + Jean-Luc, PLC + Control Software debugging, , Test TCU<->Drive,  
Entry  Tue Feb 26 20:45:41 2019, Drive Team- Ino&Thierry, Telescope Operations, General, Tracking debug,  
Entry  Tue Feb 26 20:47:15 2019, Drive Team- Ino&Thierry, Telescope Operations, General, Polaris point for mirrors aligment,  
Entry  Wed Feb 27 20:33:17 2019, Drive Team- Ino&Thierry, Telescope Operations, General, Polaris point for mirrors aligment,  
Entry  Thu Feb 28 19:56:55 2019, Drive Team- Ino&Thierry, PLC Software and Configuration, , Tracking debug and setup,  
Entry  Thu Feb 28 20:01:44 2019, Drive Team- Ino&Thierry, Telescope Operations, General, Polaris point for mirrors aligment,  
Entry  Tue Mar 5 14:42:22 2019, Drive Team- Ino&Thierry, Telescope Operations, General, High speed drive tests,  
Entry  Tue Apr 16 10:10:55 2019, Drive Team- Ino&Thierry, PLC Software and Configuration, , Elevation setup,  
Entry  Thu Sep 12 16:41:53 2019, Drive Team- Ino&Thierry, PLC + Control Software debugging, , ,  
Entry  Tue Apr 16 14:34:22 2019, Drive Team- Ino, Telescope Operations, Hardware, Cabling the azimuth end switches,  